Special Tools Required
Voltage Meter (with wire probes)
Amperage Meter
Incline manometer or equivalent
Tachometer
Thermometer
Start-Up Checklist
The unit will be in operational mode during
Line Voltage - check at unit disconnect |
|
|
|
|
|
|
| ||
| Volts | _________ | Volts | Volts | |||||
Motor Amp Draw: |
|
|
|
|
|
|
|
|
|
Supply Motor Amps | L1 | _________ | Amps | L2 | _________ | Amps | L3 | _________ | Amps |
Exhaust Motor Amps | L1 | _________ | Amps | L2 | _________ | Amps | L3 | _________ | Amps |
Fan RPM: | Supply Fan RPM _ _____________ |
|
|
| |
| Exhaust Fan RPM______________ |
|
|
| |
Correct fan rotation direction: | Supply Fan | Yes | / | No | |
|
| Exhaust Fan | Yes | / | No |
Start-Up Checklist for Evaporative Cooler
Evaporative coolers are an integral part of the unit and must be set up properly.. Doing so will ensure correct operation and avoid water or leakage problems.. HRE units will have one or two evaporative coolers.. The following checklist must be completed for each evaporative cooler.. Qualified personnel should perform installation and be present for
| Indirect Evap | Direct Evap |
Connect overflow line (run bleed line into overflow) | o | o |
Connect drain line | o | o |
Install trap | o | o |
Connect water supply line | o | o |
For units with Auto Drain & Fill with Freeze Protection |
|
|
Install, wire, and provide power to components | o | o |
Confirm temperature and timer settings | o | o |
Pump filter clean and installed properly | o | o |
Saturate media per IOM | o | o |
Adjust | o | o |
Check for water carryover | o | o |
Connect ‘Call for Cooling’ signal | o | o |
Remove jumper wire | o | o |
30