Installation Instructions for:
NV-45 w/Horizontal Discharge
Step 1 Mounting the Unit
Arrangement HZ can be mounted on a curb with an equipment support (see curb inst.) or on three equipment supports (figs. 1&4).
Arrangement HZ can also be used for indoor applications mounted hanging (fig. 5), inline as part of an air handling system, or base mounted. Mounting hardware to be provided by others.
In any case, adequate support of the unit is required.
Equipment
Support
Footprint
C
L
A
(fig.1)A
A | 441/4" |
L |
|
|
|
C
L
C
L
Step 2 Attach Ductwork to Unit Discharge
Chart and drawing (fig.2) below shows opening size (ID) and location for a discharge collar. Also included is the recommended straight duct length for optimal performance. Greenheck recommends attaching ductwork to collar using a rubber duct section at the unit to eliminate vibration.
Step 3 Attach Ductwork to Unit Intake
For
Recommended Duct Size/Location and Intake Dimensions
Minimum Straight Duct Length - 54”
Typical Installations
16 23
16
12
(fig.2)
48
43 |
(fig.3)
DISCHARGE
DISCHARGE
INTAKE
INTAKE
(fig.4)
Roof mounted arrangement HZ
with weatherhood, mounted on three equipment supports. Ductwork is attached to discharge collar with rubber boot transition.
(fig.5)
Arrangement HZ shown as an indoor hanging installation with intake and discharge ductwork installed.
(Hanging support structure for unit is by others).