Installation Instructions for:
SLAB, RAIL, AND CURB MOUNTING
GREENHECK
®
Before beginning this installation:
Make sure that there is room to access the unit from all sides.
Make sure inlet of unit is located well away from any exhaust fans.
NV | Unit |
|
Spreader Bar
In | ta | k | e |
| |||
|
| ||
|
|
|
Lifting Lugs (4)
1a. Slab Construction
Recommended Size: 1ft. wider and longer than total unit size. Recommended Material: Concrete at least 4" thick.
Slab should be set and leveled on a sufficient bed of gravel for proper drainage.
1b. Install Unit
Use a crane and spreader bar to prevent damage to unit. Lifting lugs are provided as shown in illustration.
Its is highly recommended that all accessory items be lifted separately and attached after the NV unit is in place.
Unit may be fastened to slab through lifting lugs.
6