INSTALLATION
17PNEG-1521 Commercial Direct Gear Drive Bin Sweep Auger
5. OUTER UNLOAD TUBE ASSEMBLY INSTALLATIONA. On bins > 60’ in diameter, loosen or unbolt the 30”
Connecting Band from the outer Unload Tube
Assembly.
B. Position the outer Unload Tube Assembly flush
against the inner Unload Tube Assembly, aligning
the two keyways so that they are inline, and
making sure all of the Intermediate Wells are level
with the Centerwell.
C. Slide the Connecting Band until it is equally
positioned over both the Unload Tube Assemblies.
Position the Connecting Band so that it is aligned
with the keyways on the Unload Tubes.
D. Secure the Connecting Band with eight
(8) 3/8" x 1-½” Hex bolts and Stover nuts.
Inner Unload Tube
Outer Unload Tube
Connecting Band Bolts
and Nuts Removed
CENTER OF BIN
Inner Unload Tube
Outer Unload Tube
Keys are Aligned Connecting Band
Connecting Band Centered and
Aligned Over Keys
3/8” x 1-1/2” Hex Bolts
CENTER OF BIN
CENTER OF BIN
FIG. 5-A
FIG. 5-B
FIG. 5-C
3/8” Stover Nuts