INSTALLATION
21PNEG-1521 Commercial Direct Gear Drive Bin Sweep Auger
A. Make sure that all gates are fully closed.
B. Pin the Inside Intermediate Control Rod to the
Centerwell Control Rod, by using a 5/16" x 1-¾”
Hex bolt and Hex nut through the aligned hole.
8. RACK & PINION INSTALLATION
C. Slip the Rack & Pinion tube over the Centerwell
Gate Control Rod, and slip the Outside
Intermediate Well Adapter pipe into the Outside
Intermediate Control Rod. Align the holes to the
Centerwell Control Rod and the Outside
Intermediate Well Control Rod with the matching
holes on the Rack and Pinion. Make sure the
Rack & Pinion is fully extended towards the bin
wall.
D. Attach the Rack & Pinion to the Control Rods
using two (2) 5/16" x 1-¾” Hex bolts and Hex nuts.
5/16” x 1-3/4”
Hex Bolt
5/16” Hex Nut Rack and Pinion Assembly
Fully Extended
Rack and Pinion
5/16” x 1-3/4”
Hex Bolt
Rack and
Pinion Tube
Centerwell
Control Rod
5/16” x 1-3/4”
Hex Bolt
5/16” Hex Nut Outside Intermediate
Well Adapter Pipe
FIG. 8-A
FIG. 8-B
FIG. 8-C
Outside Intermediate
Control Rod