INSTALLATION - MODEL L20 DVF-2 ONLY
Direct Vent Retrofit Of Existing Chimney System - An existing
Model # | Brand: SECURITY / Description | Model # | Brand: SIMPSON |
SV4MCK | Masonry Chimney Conversion Kit | 934 | Masonry Chimney Conversion Kit |
| cap adapter, masonry cover, black adapter (to flex), 2 |
|
|
| gear clamps |
|
|
SV4CCK1 | Factory Built Chimney Conversion Kit – for 6” I.D., 1” | 931 | Factory Built Chimney Conversion Kit A – for 6” |
| insulation. |
| I.D.; Only compatible w/specific brands – Contact |
|
|
| Vent Manufacturer |
SV4CCK2 | Factory Built Chimney Conversion Kit – for 7” I.D., 1” | 932 | Factory Built Chimney Conversion Kit B – for 6”, 7” |
| insulation; 8” I.D., 1” insulation; 6” I.D., 2” insulation. |
| & 8” I.D.; Only compatible w/specific brands – |
|
|
| Contact Vent Manufacturer |
SV4CCK3 | Factory Built Chimney Conversion Kit – for 10” I.D., 1” | 933 | Factory Built Chimney Conversion Kit C – for 7” & |
| insulation; 7” I.D., 2” insulation; 8” I.D., 2” insulation. |
| 8” I.D.; Only compatible w/specific brands – Con- |
|
|
| tact Vent Manufacturer |
MODELS L20
VERTICAL VENT TERMINATION REQUIREMENTS
These instructions should be used as a guideline and do not supersede local codes in any way. Install vent according to local codes, these instructions, the current National Fuel Gas Code
Terminate multiple vent terminations according to the installation codes listed above.
Terminate single vent caps relative to building components according to the following chart & illustration. The vent/air intake termina- tion clearances above the high side of an angled roof is as shown in the following chart:
Termination Heights For Vents
Above Flat or Sloped Roofs
Horizontal Overhang
Roof Pitch | Feet | Meters |
Flat to 6/12 | 1 | 0.3 |
6/12 to 7/12 | 1.25 | 0.38 |
7/12 to 8/12 | 1.5 | 0.46 |
8/12 to 9/12 | 2 | 0.61 |
9/12 to 10/12 | 2.5 | 0.76 |
10/12 to 11/12 | 3.25 | 0.99 |
11/12 to 12/12 | 4 | 1.22 |
12/12 to 14/12 | 5 | 1.52 |
14/12 to 16/12 | 6 | 1.83 |
16/12 to 18/12 | 7 | 2.13 |
18/12 to 20/12 | 7.5 | 2.29 |
20/12 to 21/12 | 8 | 2.44 |
•Venting terminals shall not be recessed into a wall or siding.
•Ref. NFPA 54 / ANSI Z223.1, 7.6, fig. 13: Gas Vent Termination locations for listed Caps, 12 inches or less in size, at least 8 feet from a vertical wall.
2 Ft. Min.
Vent
Termination
Storm
Collar
Flashing
Concentric Vent Pipe
2 Ft. Min.
Lowest
Discharge
Opening
* H
X
12
Roof Pitch is X/12
1 inch (25.4 mm) Minimum Clearance to Combustibles
*H = Minimum height from roof to lowest discharge opening of vent.