Installation and Configuration
1.Remove the 3U battery access panel on the front of the
Battery Door Captive Screws
!
UPStation GXT | ! |
- +
AC INPUT BATTERY UPS ON | BYPASS |
3U Battery Access Door and
Battery Bezel
Retaining
Battery ConnectorsRetaining screw bracket (one of two)
2.Once the captive screws are loosened, tip the panel forward and lift to remove it from the main cabinet.
3.Unpack the
4.Line up and slide in the battery pack while holding the internal connector out of the way.
5.Connect the electrical cables to each battery pack with the two slotted battery connectors.
6.Install the battery retaining brackets supplied in the accessory box.
7.Install the battery access panel and tighten the captive screws.
5.3Connect the Internal Batteries Using the External Connector
The connector attaches to the UPS in both the open and closed position using two screws. The picture on the left shows the connector in the open position, as shipped.
When the UPS is installed, remove the two screws to release the connector. Plug the connector into the socket. The internal batteries are now connected to the UPS electronics. Install the two screws to secure the connector in the closed position.
Remove these screws to release connector
5.3.1Storage
If the UPS is to be shipped or stored for an extended time, the connector should be removed and attached in the open position, as shown above. This will minimize any standby current drain on the batteries.
5.4Connect Input/Output Power
The Power Distribution box is shipped separately for easier handling of the UPS while the UPS is being placed in its final position.