Installation and Configuration
5.4.1Attach Power Distribution Box
Whenever the power distribution box is not attached to the UPS, the cover must be slid over the elec- trical connections to prevent damage or injury.
To attach the
1.Loosen the white cover over the electrical connections by backing out the three screws securing the cover one turn each.
2.Slide the cover open to expose the electrical connectors.
3.Gently retighten the three screws loosened in Step 1.
4.Align the connectors on the box and UPS.
5.Push the box into place.
6.Holding the box firmly against the UPS, tighten the three captive mounting screws until the box is secure. Do not overtighten.
Figure 6 PD-L630 power distribution box
FRONT of PD-L630 power distribution box
UPS
MAITANENCE BYPASS
AVAILABLE
UPS
ON | ON |
|
|
| |
OUTPUT |
| |
BREAKER | OUTPUT | |
20A | 240V~/T | |
| BREAKER | |
OFF |
| 20A 240V~/T |
OFF |
| |
|
|
|
| INPPUT |
BREA | 30A | ON |
|
|
OUTPUT ONLY |
| |
| CB DOES NOT | |
CONNECT BYPASS | POWER TO | |
MANUAL |
| |
| BYPASS SWITCH. |
These captive screws attach the power distribution box to the UPS
INSIDE FACE of
CONNECTOR PROTECTIVE COVER DO NOT REMOVE SCREWS PRIOR TO INSTALLATION OF BOX ON UPS
- SLIDE COVER TO EXPOSE CONNECTOR
UPON REMOVAL OF BOX FROM UPS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Loosen these three | ||||
|
|
| |||||
|
|
| |||||
Slide the cover over | screws to move the | ||||||
the connectors when | cover. Retighten the | ||||||
the power distribution | screws after moving | ||||||
box is removed from | the cover over the | ||||||
the UPS. | connectors or off the | ||||||
|
|
| connectors. |
16