Installation
1.Using template provided, determine mounting location.
2.Drill holes and attach mounting hardware (not included).
IMPORTANT: THE HARDWARE AND THE SUPPORTING STRUCTURE MUST BE CAPABLE OF SUPPORTING A MINIMUM 150 LB. LOAD.
NOTE: All installation should be done to meet local building code.
3.Mount cabinet on wall and securely tighten hardware.
4.Replace motor/blower assembly in cabinet. Secure two wing nuts on blower base. Reconnect motor electric cord plug assembly and heater plug.
5.Replace intake grille with louvers facing down and refasten knurled nuts.
FIELD POWER WIRING
WARNING: ALL AIR CURTAINS SHOULD BE INSTALLED BY QUALIFIED PERSONNEL.
1.Before wiring, be sure that available power supply, voltage, phase, and frequency corresponds to that specified on heater rating plate. In addition, make cer- tain that service capacity is sufficient to handle load imposed by the equipment.
2.Install all wiring, protection and grounding in accor- dance with the National Electrical Code (NEC) and
all local requirements.
WARNING: THIS FAN HAS AN INTERNAL SELF RESETTING THERMAL OVERLOAD PROTECTOR. ALWAYS DISCONNECT FROM POWER SUPPLY BEFORE SERVICING.
3.Remove two screws from switch box and remove cover.
4.Run proper size copper power supply conductors from the field power supply disconnects, (supplied by others) with insulation rated minimum 75˚C (167.0˚F). One set of conductors from 240VAC, 50/60Hz supply source shall be routed through the 3/4 inch conduit knockout, using a suitable knockout connected to the contactor contact terminals marked L1, L2. A separated set of supply conductors from a 120VAC,
50/60 Hz supply source shall be routed through 1/2 inch knockout using a suitable knockout connector, for connection of the fan circuit. The fan supply conductors are to be marked L1, N (see diagram on
inside heater wiring compartment cover and Figure 5).
5.The heater control box must have an unbroken electrical ground to minimize personal injury if an electrical fault should occur.
FIELD CONTROL WIRING
Electric heater is equipped with a
6.Replace heater control box cover.
7.Unit is ready for operation.
8.Restore power.
NOTE: Air curtain has high/low selector switch. See Operation section for proper setting instructions.
9.Upon completion of all installation, inspect unit for excessive vibration during operation. If excessive vibration is noticeable, disconnect power supply. Inspect mounting installation and refer to Troubleshooting Chart for probable cause.
Figure 5 - Wiring Diagram