3-5. Installing Voltage Sensing Lead And Motor Start Control Adjustment

1

Front

2

3

4

CV CC INT. EXT.

1 2 3

RC3

1Center Baffle

2Circuit Board PC1

3Jumper Plug

4Receptacle RC3

Internal (INT) and external (EXT) are stamped on PC1 just above RC3. Unit is shipped with jumper plug in internal (INT) position.

To install voltage sensing lead, proceed as follows:

5Clamp

6Cord

Connect ring terminal on end of cord using screw in clamp. Crimp clamp tabs around cord.

7 Strain Relief

Slide strain relief onto cord approximately 6 in (152 mm) from cord end.

10

6

7

8

9

For CC operation, connect voltage sensing lead to workpiece.

5

Remove upper hole plug from rear panel.

Insert cord into opening in rear panel, and secure strain relief into opening.

8 Terminal Strip 1T

Connect voltage sensing lead to terminal strip 1TK at lead 42.

9 Voltage Sensing Lead

For constant current welding (CC), place jumper plug in the EXT position. Connect voltage sensing lead to workpiece.

For constant voltage welding (CV), place jumper plug in the INT position. Do not install voltage sensing lead.

10 Potentiometer R70

To adjust motor ramp speed, remove protective cap (if present), and adjust potentiometer R70 using a small nonconductive screwdriver. Rotating R70 clockwise increases the time it takes the motor to ramp up to speed.

Reinstall wrapper.

Work . Contactor cord only on standard model.

Rear View

Tools Needed:

1/4 in

150 035-B / Ref. 143 328-K / 149 920-B

OM-1078 Page 11

Page 15
Image 15
Miller Electric WC-115A manual Work . Contactor cord only on standard model