fireplace framing
Firebox framing can be built before or after the appliance is set in place. Construct firebox framing following Figures 8 through 11 and the chart below for your specific installation requirements. See Figure 1 on Page 6 for firebox dimensions. The framing headers may rest on the top of the firebox standoffs.
The firebox may be installed directly on a combustible floor or raised on a platform of an appropriate height. When the firebox is installed directly on carpeting, tile, or other combustible material, other than wood flooring, the firebox shall be installed on a metal or wood panel extending the full width and depth of the enclosure.
WARNING
Do not fill spaces around firebox with insulation or other materials. This could cause a fire.
|
| " | |
| 3/ |
| |
| 46 | 4 | " |
|
| ||
| 3/ | ||
|
| 51 | 8 |
400: |
|
| |
500: |
|
|
400: 2413/16"
500: 3013/16"
400: 401/4"
500: 461/4"
400: 661/8"
500: 725/8"
400: 123/4"
500: 16"
400: 331/16" 500: 365/16"
205/16"
400:2413/16"
500:3013/16"
Figure 8 - Corner Installation
341/4"
400: 401/4"
500: 461/4"
Figure 10 - Stud Location
203/4"
|
|
|
|
|
400: 401/4" |
|
|
|
|
| 1/2" or 5/8" | |||
| ||||
500: 461/4" |
|
|
|
|
Figure 9 - Inside Chase Installation
400:2413/16"
500:3013/16"
203/4"
|
|
|
|
|
|
400: 403/4" |
|
| 1/2" or |
| 5/8" |
| |||||
|
| ||||
500: 463/4" |
|
|
|
|
|
Figure 11 - Recessed Installation