7 Installation Motorola recommends that only qualified personnel undertake the installation of a PTP 600
Series Bridge solution.
7.1 Preparation
Before proceeding with the installation you should:
• Check the contents of all packages against the parts lists shown in the packing list.
• Ensure that you have the correct tools for the job.
• Ensure that you are qualified to undertake the work.
• Ensure that you have taken the correct safety precautions.
• Have completed the site planning as described in section 6 “Site Planning”.
7.2 Installation Procedure
The 600 Series installation procedure consists of the following steps:
• Mounting the ODUs, section 7.6
• Connecting up, section 7.7
• Mounting the PIDU Plus units, section 7.7.8
• Powering Up, section
7.7.10
• Aligning the ODUs, section 7.7.11
7.3 Tools Required
The following specific tools are required to install a PTP 600 Series Bridge in addition to
general tools:
• 13mm Spanner / Wrench
• RJ45 Crimp Tool
• IBM Compatible Personal Computer (PC) running Windows 98 or later with 10, 100 or
1000 BaseT Ethernet (Ability to change IP settings easily is recommended)
• Either Internet Explorer version 6 or higher, or FireFox 1.5 or higher are recommended.
• Ethernet patch cable
• 6mm general purpose crimp tool for the grounding lug (optional for Lightning Protection)