6. Install Main Cable

S3.15 Assembly and Maintenance Guide

6. Install Main Cable

Note: All pulleys are installed in the frame assemblies. As you begin each new step, remove the fasteners and pulley. Feed the cable around the pulley as shown, and then replace the fasteners and finger tighten. Wrench tighten all pulley fasteners once you have completed the installation of each cable assembly.

A.Start at the Top Beam and feed the threaded end of Main Cable 130197 over one 4½-inch pulley. Attach the pulley to the Top Beam using

one 4-inch hex head bolt

two 1¹⁄₄-inch shoulder spacers one locknut

B.Feed the cable over the second 4½-inch pulley. Attach the pulley to the Top Beam using

one 4-inch hex head bolt

two 1¹⁄₄-inch shoulder spacers one locknut

C.Feed the cable over the upper 3½-inch pulley located in the Press Arm assembly. Attach the pulley to the Press Arm assembly using

one 2-inch zinc hex head bolt two zinc flat washers

one zinc locknut

D.Feed the cable over the upper 3½-inch pulley located in the Main Upright. Attach the pulley to the Main Upright using

one 4-inch hex head bolt

two 1¹⁄₄-inch shoulder spacers one locknut

Pulley assemblies

4½-inch Pulley

1 - bolt

2 - shoulder spacers

1 - locknut

3½-inch Pulley (used on gray painted parts)

1 - bolt

2 - shoulder spacers

1 - locknut

3½-inch Pulley (used on titanium parts)

1 - zinc bolt

2 - zinc washers

1 - zinc locknut

3½-inch Pulley (used on gray painted parts)

1 - bolt

2 - washers

1 - locknut

A B

CStep 6. Install Main Cable

D

1

2

3

4

5

6

Step 6. Install Main Cable