A

SANbox 9000Series Chassis Replacement Guide

Reinstall Power Supply Blades

NOTE

Power Supply blade installation is easier when installed after the Fan blade below it.

Open the Power Supply blade latch and slide the blade into the chassis until it contacts the midplane connector.

Rotate the latch right-to-left to lock the Power Supply blade in place.

Reinstall I/O Blades

Install the I/O blades and panels in the new chassis matching the slot label on the blade with the chassis slot.

Slide the I/O blade into the slot guide until it makes contact with the midplane connector. Rotate the blade latch upward to lock the I/O blade in place.

Reconnect the Fibre Channel port cables according to their labels.

Reconnect Ethernet and Serial Cables

Reconnect the Ethernet and serial cables to the CPU blades or Maintenance Panel.

Reconnect HyperStack cables to the CPU blades.

Power Up the Switch

Reconnect power cords to the Power Supply blades. Fasten the restraint bails on the plugs.

Move the On/Off switches on both Power Supply blades to the On position.

59244-00 A

7

Page 7
Image 7
Q-Logic 59244-00 A manual Reinstall Power Supply Blades, Reinstall I/O Blades, Reconnect Ethernet and Serial Cables