QHT Boiler manual Thermostat, Note Power failure reference page

Models: Boiler

1 40
Download 40 pages 34.95 Kb
Page 25
Image 25
Note: Power failure reference page 9.

Note: Power failure reference page 9.

Thermostat

NOTE: All wiring must be done in accordance with applicable state, local and national codes. Use only copper conductors.

3Wood installed in combination with a oil/gas boiler

Note: The operation of the gas boiler must be verified for acceptable operation before and after installation of the add-on appliance by a gas fitter who is recognized by the regulatory authority.

PIPING NOTES:

CAUTION

1.This drawing is meant to show system piping concept only.

2.The installer is responsible for all equipment & detailing required by local codes.

3.Discharge of Pressure Relief Valve must be piped without valves to within 3” of the floor.

4.Where required, Low Water Cutoff must be installed in the Supply piping of the oil/gas boiler.

5.DO NOT interfere with the normal delivery of heated water from the original boiler to the system.

6.Make sure that excessive pressure will not be developed in any portion of the boiler or system through properly sizing the expansion tank.