SECTION 5: HEATER INSTALLATION

SECTION 5: HEATER INSTALLATION

SECTION 5: HEATER INSTALLATION 5.1 General

Heaters are designed for installation above 2.5 m. These heaters must be installed within the heated space. Duct delivery systems are not permitted with axial fans.

5.2 Handling

All CTU heaters are supplied secured to a wooden pallet and shrink wrapped. Use the pallet to support the heater during handling and installation. When handling or supporting the heater from below, ensure that the weight is taken at the support points.

Figure 2: Suspension Methods

5.3 Shelf Mounting and Suspension

SECTION 5: HEATER INSTALLATION 5.1 General WARNING

Crush Hazard

Use 10 mm steel drop rod minimum.

Failure of the supports can result in death, injury

or property damage.

For typical suspension See Page 9, Figure 2.

Unistrut 5.2 Handling Channel Nut

Washer Figure 2: Suspension Methods5.3 Shelf Mounting and Suspension

Nut

10 mm

Steel Manual background

Drop Rod

10 mm Steel Manual background Drop Rod

Nut Washer Manual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual background

Riv

Nut

Insure all suspension hardware is torqued to a minimum

of 27 Nm (20 ft lbs)

Cone Point

Set Pin

Window

Clamp

Unistrut Manual background

Support Points

9