Page 12 | SERIES 28A BOILER INSTALLATION AND OPERATION INSTRUCTIONS |
Observation Port Installation
1.Screw the four
2.Place the observation port cover assembly over the studs and install the washers and nuts. Tighten the nuts uniformly.
Smokehood Installation, Figure 10
1.Screw the four
2.Apply smokehood insulation tape to smokehood.
3.Place the smokehood over the studs and install the washers and nuts. Tighten the nuts uniformly.
4.Apply the 1/8" x 3/4" x 18" strip of insulating tape to the damper anchoring angle, Figure 10.
5.Fully open the slide damper and leave it ready for adjustment during burner light off.
Figure 10 - Smokehood Assembly