2.0Thermal Performance:

Marley / Sigma 1000/1200 CoolingTower / Specifications: Base

Specifications

Specification Value

2.0Thermal Performance:

15

2.1

The tower shall be capable of cooling

Your reason for purchasing a cooling tower is to obtain a con-

 

_____ GPM of water from ____ °F to

tinuing flow of cooled water as defined in the first paragraph at

 

_____ °F at a design entering air wet-

left. If the tower that you purchase is incapable of performing

 

bulb temperature of _____ °F. The cool-

as specified, then you will not have received full value for your

 

ing tower manufacturer shall guarantee

money.

 

that the tower supplied will meet

Bear in mind that the size—and cost—of a cooling tower var-

 

the specified performance conditions

 

when the tower is installed according

ies directly with its true thermal capability. This paragraph is

 

to plans.

intended to protect you against either intentional or inadvertent

 

 

under sizing of the tower by the manufacturer. Judging the level

2.2

The purchaser will arrange for an

of performance of a cooling tower on critical processes is never

 

on-site thermal performance test, to

easy, and the potential risk of a non-performing cooling tower

 

be conducted in the presence of the

usually causes the requirement for a mandatory acceptance test

 

manufacturer and owner, and under

to be very desirable.

 

the supervision of a qualified, disinter-

Your contract with the successful bidder should establish the

 

ested third party in accordance with

 

CTI (Cooling Technology Institute) ATC-

acceptable remedies for missed performance, which might

 

105 standards during the first full year

include:

 

of operation. If the tower fails to per-

• The addition of one or more cells of tower, as necessary, to

 

form within the limits of test tolerance,

 

then the cooling tower manufacturer

bring the cooling tower to the specified level of performance.

 

will install additional cells and/or make

This is usually limited to the scope of work as defined in the

 

such corrections as are agreeable to

specs, which means that you (the owner) will have to pay for

 

the owner and shall pay for the cost of

the additional basin, wiring, starters, piping, etc.

 

a retest. If the tower still fails to per-

• The reimbursement of a portion of the total contract price equal

 

form as specified, then the manufac-

 

turer shall make such reimbursements

to the percentage deficiency in performance.

 

as are appropriate and agreeable to the

Under no circumstances should you allow the manufacturer to

 

owner to compensate for the perfor-

 

mance deficiency.

re-pitch the fans to increase motor brake horsepower above that

 

 

shown in the proposal. That creates additional operating costs

 

 

that will continue for the life of the tower—and imposes no pen-

 

 

alty on the manufacturer.

 

95°

 

 

 

 

 

 

 

90°

 

 

 

 

 

 

 

85°

 

 

 

 

 

 

(°F)

 

 

 

 

 

 

 

TEMP.

80°

 

 

 

 

 

 

 

 

 

 

 

 

5°F RANGE

WATER

 

 

 

 

 

 

75°

 

 

 

 

 

10°F RANGE

 

 

 

 

 

 

15°F RANGE

 

 

 

 

 

 

 

COLD

70°

 

 

 

 

 

 

 

 

 

 

 

 

 

 

65°

 

 

 

 

 

 

 

60°

 

 

 

 

 

 

 

55°

 

 

 

 

 

 

 

50°

55°

60°

65°

70°

75°

80°

WET BULB TEMP. (°F)

Typical cooling tower performance curve.
Page 15