Marley / Sigma 1000/1200 CoolingTower / Specifications: Base
Specifications | Specification Value |
2.0Thermal Performance:
15
2.1 | The tower shall be capable of cooling | ■Your reason for purchasing a cooling tower is to obtain a con- |
| _____ GPM of water from ____ °F to | tinuing flow of cooled water as defined in the first paragraph at |
| _____ °F at a design entering air wet- | left. If the tower that you purchase is incapable of performing |
| bulb temperature of _____ °F. The cool- | as specified, then you will not have received full value for your |
| ing tower manufacturer shall guarantee | money. |
| that the tower supplied will meet | Bear in mind that the |
| the specified performance conditions | |
| when the tower is installed according | ies directly with its true thermal capability. This paragraph is |
| to plans. | intended to protect you against either intentional or inadvertent |
|
| under sizing of the tower by the manufacturer. Judging the level |
2.2 | The purchaser will arrange for an | of performance of a cooling tower on critical processes is never |
| easy, and the potential risk of a | |
| be conducted in the presence of the | usually causes the requirement for a mandatory acceptance test |
| manufacturer and owner, and under | to be very desirable. |
| the supervision of a qualified, disinter- | Your contract with the successful bidder should establish the |
| ested third party in accordance with | |
| CTI (Cooling Technology Institute) ATC- | acceptable remedies for missed performance, which might |
| 105 standards during the first full year | include: |
| of operation. If the tower fails to per- | • The addition of one or more cells of tower, as necessary, to |
| form within the limits of test tolerance, | |
| then the cooling tower manufacturer | bring the cooling tower to the specified level of performance. |
| will install additional cells and/or make | This is usually limited to the scope of work as defined in the |
| such corrections as are agreeable to | specs, which means that you (the owner) will have to pay for |
| the owner and shall pay for the cost of | the additional basin, wiring, starters, piping, etc. |
| a retest. If the tower still fails to per- | • The reimbursement of a portion of the total contract price equal |
| form as specified, then the manufac- | |
| turer shall make such reimbursements | to the percentage deficiency in performance. |
| as are appropriate and agreeable to the | Under no circumstances should you allow the manufacturer to |
| owner to compensate for the perfor- | |
| mance deficiency. | |
|
| shown in the proposal. That creates additional operating costs |
|
| that will continue for the life of the |
|
| alty on the manufacturer. |
| 95° |
|
|
|
|
|
|
| 90° |
|
|
|
|
|
|
| 85° |
|
|
|
|
|
|
(°F) |
|
|
|
|
|
|
|
TEMP. | 80° |
|
|
|
|
|
|
|
|
|
|
|
| 5°F RANGE | |
WATER |
|
|
|
|
|
| |
75° |
|
|
|
|
| 10°F RANGE | |
|
|
|
|
|
| 15°F RANGE | |
|
|
|
|
|
|
| |
COLD | 70° |
|
|
|
|
|
|
|
|
|
|
|
|
| |
| 65° |
|
|
|
|
|
|
| 60° |
|
|
|
|
|
|
| 55° |
|
|
|
|
|
|
| 50° | 55° | 60° | 65° | 70° | 75° | 80° |
WET BULB TEMP. (°F)