A.Refer to the nameplate at the rear of the freezer for specific electrical requirements. Make sure the power source in the building matches the freezer nameplate requirements. Bring the wires into the junction boxes through the access holes in the bottom rear of the freezer. Figure 4.

NOTICE

Three phase freezers in areas of unbalanced electrical loads require special attention when connecting input electrical power. The unbalanced leg of power (called wild or high) must be connected to L2 in the junction box.

NOTICE

Verify actual voltage. Machine is equipped with a transformer to supply a control circuit. You will need to check voltage on terminal C1 and C2 on EACH control board. (Located behind decorative header panel on front of machine.) Transformers are located behind electrical panel enclosing control boards. Access these by removing top panel of machine. Actual transformer voltage should read 20-28 V.A.C.

B.Remove the lower back panel and the two junc- tion box covers located at the bottom of the freezer.

C.lnstall permanent wiring according to local code.

D.Check the auger shaft rotation by placing the MAIN DRIVE switch in the CLEAN position.

Auger shaft rotation is clockwise as viewed through the clear plastic front door. If the rotation is not clockwise, turn main electrical power OFF. Then reverse L1 and L3 electrical power lines to the junction box (three phase only). Re-check auger shaft rotation. Figure 5.

Figure 5. Auger Rotation

2.5 MIX PUMP

A.Mix Pump Hose Installation

Follow the steps below to install the mix pump hose.

1.Turn pump on.

2.Feed one end of mix pump hose into the entering or pick-up hose side (left) of black cover.

3.Gently push the hose into the black cover until it begins to feed.

4.Allow the hose to feed itself thru the pump until 6" (15cm) remains on the entering side.

6" (15cm)

Figure 6. Mix Hose Installation

5