1.Connect the female end of the power cord to the power receptacle at the rear of the hub (FIGURE 1-1on page 1-2).

2.Route the power cord down the right side and along the bottom of the cabinet.

3.Route the power cord up through the cutout to the power distribution unit at the left side of the cabinet.

Caution The power distribution unit serves as the primary disconnect device for the hub. Do not connect the hub into a power source other than the power distribution unit. Personal injury can result if you work on a hub that is connected into another power source, since that power source may still be active when you work on the hub.

4.Connect the power cord for the tray to the power distribution unit.

If your power distribution unit has a sequencer, connect the first hub to one of the four lower outlets. Connect the second hub to one of the four upper outlets.

5.Tuck the extra length of the power cord down into the pocket beneath the power distribution unit.

2.3.7Verifying the Configuration

1.Power on all nodes and then the hub.

Note Refer to the handbook that came with your peripheral and your system installation manual for instructions on safely powering on the cabinet.

2.Make sure that the Device Active LEDs are lit for active hub ports. The Bypass LEDs for active ports should be off.

See Section 2.4, “Troubleshooting” if:

The Device Active LED for an active port is flashing

The Bypass LED for an active port is on

The Device Active LED for an active port is off

The FC-AL should now be operational.

Chapter 2 Installation 2-7

Page 29
Image 29
Sun Microsystems FC-100 service manual Verifying the Configuration