27
Model C722 Operating Procedures
Step 9
Slide the beater assembly the rest of the way into
the freezing cylinder.
Make sure the beater assembly is in position over
the drive shaft by turning the beater slightly until t he
beater is properly seated. When in position, the
beater will not protrude beyond the front of the
freezing cylinder. (See Figure 45.)
Figure 45
Repeat these steps for the other sid e of the
machine.
Step 10
To assemble the freezer door, place the door
gaskets into the grooves on the back of the freez er
door.
Figure 46
Step 11
Slide the front bearings over the baffle rods. T he
flanged edges should be against the door. DO NOT
lubricate the gaskets or front b earings.
Slide the two o-rings into the grooves on each prime
plug. Apply an even coat of Taylor Lube to the
o-rings and shafts.
Figure 47
Step 12
Insert the prime plugs into the holes in the top of the
freezer door, and push down.
Figure 48