PRESSURE TESTING HEATER GAS CONNECTIONS

4.Check all joints of gas supply piping system. Apply mixture of liquid soap and water to gas joints. Bubbles forming show a leak.

5.Correct all leaks at once.

Test Pressures Equal To or Less Than 1/2 PSIG

1.Close manual shutoff valve (see Figure 11).

2.Pressurize supply piping system by either using compressed air or opening main gas valve located on or near gas meter.

3.Check all joints from gas meter to manual shutoff valve (see Figure 12). Apply mixture of liquid soap and water to gas joints. Bubbles forming show a leak.

4.Correct all leaks at once.

PRESSURE TESTING HEATER GAS CONNECTIONS

1.Open manual shutoff valve (see Figure 11).

2.Open main gas valve located on or near gas meter.

3.Make sure control knob of heater is in the OFF position.

4.Check all joints from manual shutoff valve to control valve (see Figure 12). Apply mixture of liquid soap and water to gas joints. Bubbles forming show a leak.

5.Correct all leaks at once.

6.Light heater (see OPERATING HEATER, pages 12 through 15). Check the rest of the internal joints for leaks.

7.Turn off heater (see TO TURN OFF GAS TO APPLIANCE, page 15).

8.Replace front panel.

Open

Manual

Shutoff

Valve

Closed

Figure 11 - Manual Shutoff Valve

Control Valve Location

Gas Meter

Manual

Shutoff

Valve

Figure 12 - Checking Gas Joints

11

Page 11
Image 11
Vanguard Heating VN12, VN6A installation manual Pressure Testing Heater Gas Connections