Fig. 23 Apply sealant to the starter pipe, and fasten to stove with Phillips screws.
2.Locate the vent opening on the wall. Refer to Figures 24, 25 & 26 to determine the top of the opening centerline. It may be necessary to first position the stove and measure to find the hole location. Depending on whether the wall is made of combustible materials, cut the opening to the size shown in Figure 24. Combustible wall openings must be framed as shown in Figure 24
Vent Opening - Combustible Wall
9³⁄₈"
(240mm)
10³⁄₈"
(265mm)
Framing Detail
Vent Opening -Noncombustible Wall
| 7¹⁄₂" Dia. |
| |
| (190mm) |
| |
|
| ||
Fig. 24 | Locate vent opening. |
| |
9³⁄₈” W x 10³⁄₈” H | Firestop | ||
Wall Opening | |||
Wall Sleeve - | Ventilated Wall Plate - | ||
Open End Down | |||
Seal Around | |||
Finishing Collar | |||
|
| ||
| 27³⁄₈" |
| |
| (695mm) |
| |
| to Top of |
| |
Seal | Opening |
| |
|
| ||
Around |
| ||
Terminal |
| ||
ST400 |
|
|
Fig. 25 SDVR with Rear Vent Kit 7TFSRSK installation.
9³⁄₈” W x 10³⁄₈” H | Firestop | |
Wall Opening | Ventilated Wall Plate - | |
Wall Sleeve - | ||
Open End Down | ||
Seal Around | Finishing Collar | |
| ||
25³⁄₄" |
| |
(654mm) |
| |
to Top of |
| |
Opening |
| |
Seal |
| |
Around |
| |
Terminal |
| |
ST400 |
| |
Fig. 26 PDV20 with Rear Vent Kit 7TFSRSK installation. |
3.Measure the wall thickness and cut the wall sleeve sections to proper length (MAXIMUM 12”). Assemble the sleeve with the #8 sheet metal screws supplied. Attach the firestop plate to the sleeve end with the holes. (Fig. 32) NOTE: The wall sleeve is required in combustible walls only.
4.Install the Wall Firestop/Sleeve assembly into the wall cutout and fasten the firestop to the wall cutout framing members. (Figs. 25, 26)
5.Measure, and cut if necessary, the appropriate length of pipe section needed to make the connec- tion through the wall.
6.Slip the wall plate and trim collar over the interior end of the horizontal pipe and install into the wall sleeve. Seal the joint inside the wall plate if needed to keep cold air from being drawn into the home.
7.Connect the pipe to the inner collar. Fasten the wall plate to the pipe with three sheet metal screws. Slide the trim collar up against the wall plate to cover the screws. (Figs. 25, 26)
8.Install the vent terminal. (Figs. 25 & 26) Guide the inner and outer vent termination collars into the adjacent pipes. Double check that the vent pipes overlap the collars by 2”. Fasten the termination to the wall with the screws provided, and caulk the joint with weatherproof sealant.
Through Side Wall /
Vent Termination Below Grade
Refer to Figures 27 & 28 for minimum centerline of wall opening.
1.Attach Inner Starter Pipe, (found in with the logset), to the stove.
• Run a bead of sealant beneath the pipe bead and attach to the stove using three
20003457 | 17 |