AUTHORISED PROFESSIONAL PERSONNEL ONLY
1. Placement
The system must be installed in dry indoor surroundings free from explosion hazard. The components shall be placed on firm and level ground, and the system must be easily accessible for the purpose of maintenance procedures. The room temperature must not exceed 40 °C.
Additional
(140 mm length) facilitates maintenance ac- cess. In the absence of sufficient space the elastic feet can be used by themselves.
2. Connections
The water and
nVDMA guideline, standardised leaflet 24416
nVDE Regulations (VDE = Professional Association of German Electricians)
nRegulations issued by local utility companies
Both the required water supply and the electrical mains network connection must be configured for permanent operation. The specified connective load values are stated in the Specifications.
The water supply must be equipped with a shutoff valve, and must be connected with the
To prevent pump damage, a
In the event of excessive admission pressure or the occurrence of pressure peaks in the mains network, the installation of a pressure regulator upstream of the system is mandatory.
The motor cooling circuit within the system requires a separate
A water drain must be present at the installation site.
3. High-pressure Installation
The link between the
The permanent pipe network installation must consist of as many straight runs as possible. All
To keep pressure losses in the high- pressure lines as low as possible, the following recommendations should be used as mandatory guidelines:
Delivery | Tubing line | Hose size |
volume |
|
|
|
|
|
1000 L/h | NW 10 (3/8") | NW 8 |
|
|
|
2000 L/h | NW 15 (1/2") | NW 12 |
|
|
|
3000 L/h | NW 15 (1/2") | NW 12 |
|
|
|
4000 L/h | NW 20 (3/4") | NW 16 |
|
|
|
6000 L/h | NW 25 (1") | NW 20 |
|
|
|
It should be understood that the above guidelines still require additional allowances for the overall tubing length, the number of directional changes and armatures.
G1 |