Generac QT 5.4L owner manual Maintenance Level

Page 22

Standby Generator Sets

Service Schedule

Maintenance

Level 1

 

Level 2

 

Level 3

 

Level 4

 

Level5

 

Tasks

Recom-

Task

Required

Task

Required

Task

 

Task

Required

Task

 

mended

Comp.

to be done

Comp.

to be done

Comp.

Required

Comp.

to be done

Comp.

 

to be done

(Date-

3 months/

(Date-

Semi-

(Date-

to be done

(Date-

Bi-

(Date-

 

monthly/

Initials)

Break-in

Initials)

annually/

Initials)

Annually/

Initials)

annually/

Initials)

 

10 hrs.

 

30 hrs.

 

50 hrs.

 

100 hrs.

 

250 hrs.

 

1.Disable the unit from operating

per the first page warning.

2.Check the engine

oil level. Adjust as necessary.

3.Check the engine coolant level. Adjust as necessary.

4.Check the engine coolant thermal

protection level. Correct as necessary.

5.Check the natural gas delivery system for leaks

and correct pressure on gas engine driven units. Tighten connections as necessary.

6.Check the air inlets and outlets for debris. Clean as necessary.

7.Check the battery electrolyte level and specific gravity if accessible. Adjust as necessary.

8.Check the battery

posts, cables, and charger for loose connections, corrosion, and proper operation. Correct as necessary.

9.Check the unit wiring for loose connections, corrosion, and damage. Correct as necessary.

09/05 A .Rev SrvSchd001

11-2

Image 22
Contents QT 5.4L 100kW Models Standby Generator Sets Table of Contents  Warning   Electrical Hazards  Authorized Service Dealer Location ‹ Operation and Maintenance‹ HOW to Obtain Service IntroductionIdentification Record ‹ Data LabelEngine OIL Recommendations Equipment DescriptionCoolant Recommendations Engine Protective Devices ‹ Natural GAS Fuel System Fuel System‹ Fuel Requirements ‹ LP Fuel SystemSpecifications ‹ Cold Weather KIT Interconnections‹ Ignition Enable 14 Line Input ‹ Ignition POWER-UP Input 56 Line Input‹ Ignition Shutdown on Loss of Crank or CAM Signals 4L & 6.8L Ignition Description‹ 3-PHASE Alternators Alternator Power Winding Connections‹ FOUR-LEAD, SINGLE-PHASE Stator Generator AC Lead ConnectionsPreparation Before START-UP InstallationInitial Inspection for QT Genset Startup ‹ Preparation for START-UP START-UP Checklist‹ START-UP Inspection ‹ Engine START-UP and Transfer Operating Unit with Manual Transfer SwitchGenerator Control Operation ‹ Retransfer and ShutdownCooling System Checking Fluid LevelsMaintenance Owner Operator can Perform ‹ Cleaning the Generator Miscellaneous Maintenance‹ Changing the Engine AIR Cleaner ‹ Spark Plugs‹ Battery Maintenance Repair Parts‹ Battery ‹ Battery ReplacementService Schedule KW 150 KW Standby GAS Engine Driven Generator SetsMaintenance Level 11-3 11-4 Troubleshooting Guide Problem Cause CorrectionStandby Generator Sets Standby Generator Sets Page Assy Rotor 2390 80KB3 CPL Page Panel CB Conn BOX Page UL Circuit Breaker 225AF Page STAND, RH Control CPL C5 Page Washer Lock M10 Page MTG Base CP 5.4L 100KW DD Page Tray Battery Page Components Included in 0F1826E Page Pipe EXH Manifold 4.6L LH Page AIR Clnr BTM PLT W/CPLR 8.1L Page Tube Heater Water Page Starter 12 Volt Page Support NAT GAS Solenoid Page Support NAT GAS Solenoid Page Rear Wrap C5 Page Page Page Page Page Page Page Page Page Page Page Page Page Page Page Page Page Page Standby Generator Sets Warranty