Wiring the Inverter
To wire the main utility service panel to the GT Inverter:
1.Install conduit from the main utility service panel to the wiring box of the GT Inverter. Run the two HOT wires (L1 and L2) and ground wire from the service panel through the conduit and into the inverter wiring box.
2.Install or use an existing
3.Connect the ground wire (green or bare copper) from the ground bar in the main utility service panel to the GND bar in the wiring box.
4.Connect the L1 HOT wire (black) from the
5.Connect the L2 HOT wire (red) from the
6.Ensure all connections are correctly wired and properly torqued according to values shown in Table