B.5 in 1 FUNCTION BRACKETS on RACK-MOUNT 3U DESIGN:

(1)19” Rack installation:

Mount the 3U rack-mount in a 19-inch EIA 310 C standard rack.

19” rack width

(2)23” Rack installation:

Change the position of the two mounting brackets to mount the 3U rack-mount in a 23-inch EIA 310 C standard rack.

23” rack width

(3)Tower installation:

a.Move the mounting brackets from the front to the side and attach the brackets by screws. Then let the UPS stand with the vertical direction as the below pictures shown.

b.Rotate the control panel unit from horizontal to vertical direction.

38

39

Image 22
Contents 4K VA 20K VA UPS Declaration of Conformity RequestImportant Safety Instructions Save These Instruction System description IntroductionGeneral description Diagnostic tests System configurationFree Run Mode Efficiency Optimizer functionStorage Safety informationInstallation EnvironmentRear panel views 6KVA Rear panel With ISO 8K~10KVA Rear panel Without ISO 8K~10 KVA 12KVA Rear panel ISO and With ISO Connection to mains and loads 4000 20000 VA Or kill personnel and damage equipmentOnly required if demanded by that of local wiring rules Connecting the UPS to a Computer Computer and alarm connectionsDefault settings at the factory RS-232 Standard Interface portStarting and shutting down the UPS EPO port emergency power offUser’s guide to operations Button operationUPS meters display Control panel functionsNormal display LCD messageUPS configurations Manual test of the UPSSilencing an alarm Alarm indicatorsInterpreting UPS messages Maintenance Trouble shootingTechnical Specifications For model with 3 Phase in 1 Phase outFor Rack mount model 6K-ISO TB Connect the Battery cabinet to UPS VGD RM 6KVA3U+3U MechanicalPage Tower installation Wall installation Installation with rear Bracket