4.Slowly press the ejector in until it stops. The pin is inserted.

5.Carefully deactivate the lock and withdraw the Molex tool from the connector.

2.3Cable Management Hardware

Removing Cable Plates

1.Remove the cables from the cable plates.

See “Removing Cables From the Sun Datacenter Switch 3456” on page 2-22.

2.Starting on the right side of the Sun Datacenter Switch 3456 chassis, remove the cable plates.

a.Using an Allen wrench, remove the four M5 x 1.5 screws that secure the upper cable plate.

b.Remove the cable plate from the chassis.

c.Repeat from Step a for the next lower cable plate and continue until all six cable plates are removed.

3.Repeat Step 2 for the left side of the switch.

Installing Cable Plates

1.Starting on the right side of the Sun Datacenter Switch 3456 chassis, install the cable plates.

a.Using an Allen wrench, attach the lowest plate with four M5x1.5 screws. The support rib for the plate is on the underside. See FIGURE 2-12.

Chapter 2 Chassis Service Procedures 2-15

Image 33
Contents Sun Datacenter Switch Please Recycle Contents Fan Service Procedures Fabric Card Service Procedures Index Index-1 Preface Using Unix CommandsShell Prompts Typographic ConventionsRelated Documentation Sun Welcomes Your Comments Documentation, Support, and TrainingPage Switch Chassis Sun Datacenter Switch Overview1Parts of the Switch Chassis Power SuppliesFan Units 2Parts of the Power Supplies3Parts of the Fan Units Chassis Management Controllers4Parts of the CMCs Fabric Cards2lists the Ipmb addresses for the fabric cards Line Cards3lists the Ipmb addresses for the line cards Page Removing the Filler Panel Filler PanelsTurn the levers counter-clockwise to the unlock position 2Removing the Filler Panel Installing the Filler PanelSlide the filler panel into the chassis until it stops Tools Midplane Connector PinsInspecting the Pins on the Rear Side of the Midplane Connector identified is FC-R13-F15 Look for any light reflection inconsistencies Inspecting the Pins on the Front Side of the Midplane Connector identified is LC-C14-L10 Look at the pins as straight on. See Figure 10Locating the Bent Pin and Surrounding Pins Removing PinsRemoving a Pin With Needle-Nose Pliers 11Using Pliers to Pull a Pin Inserting PinsInstalling Cable Plates Cable Management HardwareRemoving Cable Plates 12Cable Plate Locations Removing Cable TreesIdentify the cable trees Installing Cable TreesFinger tighten the screw only Removing Cable Trays Installing Cable TraysCable Cautions InfiniBand CablesRemoving Cables From the Sun Datacenter Switch Attaching Cables to the Sun Datacenter Switch Plug the first cable into the connector at 23A Slowly move the connector Chassis Service Procedures Page Power Supply Service Procedures Powering Off Power Supplies Troubleshooting Power SuppliesRemoving a Power Supply Removing Power SuppliesSet the power supply aside Installing a Power Supply Installing Power SuppliesReconnect the power cord 6Attaching the Power Cord Powering On Power Supplies# enablepsu Troubleshooting Fans Removing FansRemoving a Fan 1Removing the Fan Installing Fans2Installing the Fan Installing a FanPage Chassis Management Controller Service Procedures Powering Off CMCs Troubleshooting CMCsRemoving a CMC Removing CMCsInstalling a CMC Installing CMCs2Installing and Securing the CMC Powering On CMCs Fabric Card Considerations Fabric Card Service Procedures1Fabric Card Status LEDs Troubleshooting Fabric CardsInspecting Fabric Cards Inspecting the Fabric Card iTRAC ConnectorsLook for any closed over or contaminated holes Inspecting the Retainers Inspecting the Fans# deactivate fc 14 Deactivating FC Powering Off Fabric CardsRemoving a Fabric Card Removing Fabric CardsInstalling a Fabric Card Installing Fabric CardsFabric Card Service Procedures # activate fc 14 Activating FC Powering On Fabric CardsCheckvoltages Checkswitches Showtemps Page Line Card Considerations Line Card Service Procedures1Line Card Status LEDs Troubleshooting Line CardsInspecting Line Cards Inspecting the Line Card iTRAC Connectors1Inspecting Line Card Connectors Inspecting the Line Card iPASS Connectors # deactivate lc 20 Deactivating LC Powering Off Line CardsRemoving a Line Card Removing Line CardsStop when the line card is halfway out. See Figure 5Turning Filler Panel Lock Levers Counter-Clockwise 6Installing the Filler Panel Installing a Line Card Installing Line Cards8Turning Filler Panel Lock Levers 9Removing the Filler Panel # activate lc 20 Activating LC Powering On Line CardsCheckvoltages Checkswitches Showtemps Page Index Page Switchover Clia command, 5-3,5-6