2.Start on the front right corner of the Sun Datacenter Switch 3456 chassis.
a.Remove all screws from the front of the cable tree.
b.Remove all but the upper two screws from the right side of the cable tree.
c.While a helper lifts the weight of the cable tree, remove the two remaining screws from the right of the cable tree.
d.Lift the cable tree away from the chassis.
3.Repeat Step 2 for the cable tree on the front left corner of the switch chassis.
▼Installing Cable Trees
Note – Two people are required to install the cable trees. One person must hold the weight of the tree for an extended time.
1.Identify the cable trees.
The cable trees are symmetrical and their orientation for installation can be difficult to determine. When properly installed, the fluted branches of the tree point forward, with the fluting on the underside of the branches. The top surface of all branches is smooth. See FIGURE
Chapter 2 Chassis Service Procedures