4.2The different server and UPS shutdown sequences

4.2.1 Extended power outage, shutdown initiated by the Shutdown Timer

During battery backup time, the Shutdown Timer of the Network Management Card is reached: after a user- defined backup time period, the shutdown of all servers is initiated, followed by the UPS shutdown (depending on its configuration). The UPS restarts when utility power is restored (depending on its configuration).

ZShutdown Duration: Maximum value of shutdown times of the Network Shutdown Modules and UM- Clients subscribed to the card and depending on the main UPS outlet. This value is updated each time a client subscribes/ unsubscribes.

ZShutdown Duration 1 (2): Maximum value of shutdown times of the UM-Client subscribed to the card and dependent on outlet 1 (2). This value is updated each time a UM-Client dependent on outlet 1 (2) subscribes /unsubscribes.

Note: During battery operation, these values are not updated.

4.2.1.1 Main UPS outlet

Shuts down after the ShutDown Timer + Shutdown Duration after having stopped the servers Restarts when utility power is restored (possibility of programming a restart delay)

Utility

ON

OFF

ON

 

Trap 17

 

Trap 18

Trap,11, Trap 29 ShutdownTim

 

 

 

er

Shutdown

 

 

Trap 31

 

 

 

Duration

 

 

 

Trap 32

 

NSM / UMC

 

Shutdown

Reboot

Main outlet

 

 

OFF

4.2.1.2 Programmable outlet 1

Shuts down after Shutoff Delay 1 after having stopped the servers dependent on outlet 1 Restarts when utility power is restored by applying Restart Delay 1

Trap 29

ShutoffDelay 1

Restart

 

Trap 31

Delay 1

 

 

 

Shutdow

 

 

Trap 32

 

UM-Client

 

 

Outlet 1

 

OFF

T H E U N I N T E R R U P T I B L E P O W E R P R O V I D E R

Network Management Card – User Manual

34003676EN/GA

Page 48/69

Image 48
Contents E U N I N T E R R U P T I B L E P O W E R P R O V I D E R Table of Contents Network Management CardsConfiguration Configuration VIA Telnet Configuration VIA SSHMaintenance Software UPGRADE62 APPENDICES63 Tables of Alarms and EventsMGE Network Solution Connecting the UPS to the NetworkIntroduction Network Management Card or ProxyMGE supervisor Enterprise Power Manager Protecting the computers / serversMonitoring the UPSs over the network Network Shutdown modulePresentation of the Environment Sensor solution How to connect UPS / agent / networkSetting up the protection ConnectionCompatibility with the legacy Solution-Pac WAN offering Direct sending of E-mailSending text messages SMS Technical data 9/69 Installation and Configuration InstallationBasic configuration Environment SensorSupervision / Administration via a Web browser Optimising the performance of your browserUPS UPS propertiesUPS zone general information on the UPS UPS status zone essential informationBattery status zone On-line help 3 3-Phase display Normal input measurementsBattery measurements UPS ControlBy Pass measurements 17/69 UPS weekly schedule programming Shutdown parameters Important note20/69 Viewing the alarms Logs Measurements23/69 Event log System log Notification Email NotificationNotified events Mail message configuration see next Recipient ListEmail Message Settings SenderSubject 29/69 Configuration User Name and password by default are MgeupsNetwork Settings 32/69 System 34/69 Notified Applications Central Shutdown Configuration Access control 38/69 SSL Time Characteristics Status Configuration LogEnvironment Environment status Environment Settings Humidity4 Log Servers protection Set-up of the shutdown parameters Shutdown criteria managed by the Management Card Specific set-up for long autonomy installation 30 mn Shutdown when backup time is less thanControlled outlets Shutdown durationLoad shedding or sequential shutdown Sequential startupDifferent server and UPS shutdown sequences Main UPS outletProgrammable outlet 49/69 2.1 Main UPS outlet 2.2 Programmable outlet2.3 Programmable outlet 51/69 3.1 Main UPS outlet 3.2 Programmable outletNetwork 4 Off/On command Main outlet55/69 Configuring a set of cards with Mupgrade Configuration in local mode and via Telnet or SSHConfiguration in local mode Choice 1 Snmp agent configuration menu MgeupsChoice 3 Access control Choice 2 UPS parametersChoice 4 Restore default configuration Choice 5 Reset the cardConfiguration via Telnet Configuration via SSHPuTTY SSH Client Program 61/69 Maintenance Software upgradeCard firmware upgrade using Mupgrade Windows Card software upgrade via Tftp Unix and WindowsTables of alarms and events Alarm tableAppendices UPS event tableUPS 65/69 System alarm table English FrenchGlossary Programmable outlet controlled outlet Subnet maskTelnet Trap Snmp UM-Client