CDT One Event Timer Exerciser (cont’d)

How to Initiate CDT Exerciser and to start an exercise cycle every 1, 7, 14, or 28 days

From S1 screen

1)Press TEST

2)Press MORE

3)Press START TEST TIMER (to initiate Test).

If the CDT Exerciser is Factory configured for a Load Exerciser, the Controller will immediately start a load exercise. The controller will start the generator, transfer the load to Source 2 and remain in Source 2 for the duration set for EXER S2 RUN TIME in the SET menu. The controller will retransfer the load back to Source 1 after the S1 stable timer has timed out and run the generator unloaded for the duration of the S2 stop delay timer (Engine Cool Down Timer).

If the CDT Exerciser is Factory configured for a No-Load Exerciser, the Controller will immediately start a No-load exercise. The controller will start the generator and run it unloaded for the duration of the S2 stop delay timer (Engine Cool Down Timer).

Exercise will be repeated at the same time as initiated on every 1, 7, 14, or 28 days according to the selection made in the Configure CFG menu.

How to Bypass (Cancel) an exercise during an exercise cycle

1)Press BPASS

2)Allow the controller to complete the Engine cool down cycle

If the CDT Exerciser is Factory configured for a No-Load Exerciser Or allow the controller to complete retransfer to Source 1 If the CDT Exerciser is Factory configured for a Load Exerciser

How to Bypass the next exercise event and Keep the rest of scheduled events unchanged

1)Press Test

2)Press MORE

3)Press BYPASS EXER

To re-institute the next exercise event back,

press CANCL BPASS

How to initiate a new exercise start time

1)Press TEST

2)Press MORE

3)Press EXER CANCL

4)Press START TIMER TEST

How to check the next exercise event

1)From S1 OK screen, press MORE three times.

2)The unit will display the PLANT EXERCISER NEXT event in DAYS, HOURS, and MINUTES

3)Press ESC to S1 OK Screen.

Notes:

-*E* appears in the upper right hand corner of LCD screen when exercise is impending.

-For Load Exerciser, actual exercise period (ATS in S2 position)= CDT (Exerciser)

timing period +T (S1 stable Timer) timing period.

GE Zenith Controls

ZTG/ZTGD Operation and Maintenance Manual (70R-1000D)

15

Image 15
Contents GE Zenith Controls Authorized Service Table of ContentsIntroduction Mounting Safety / InstallationEquipment Inspection and Storage Final Equipment InspectionInstallation cont’d Power ConnectionsEngine Start Control Connections Installation cont’d Initial Energization GE Zenith ControlsR E T E S T Initial Energization cont’dMX150 Controller MX150 Microprocessor ControllerLCD & Keypad MX150 Microprocessor Controller cont’dCalibrate User Setting for Voltage & FrequencyStandard Features, Mstdg Option Pkg SourceStd. Features, Mstdg Option Pkg. cont’d R50S13 CDP replaces CDT Standard Features, Mexeg Option PkgOptional Accessories CDT One Event Timer Exerciser How to Set the System ClockHow to Bypass Cancel an exercise during an exercise cycle CDT One Event Timer Exerciser cont’dLoad / No-Load Clock Exerciser CDP Clock ExerciserTurn options on or OFF via keypad through the CFG menu MX150 User Setup CFG MenuChange adjustable values through the SET menu MX150 User Setup SET MenuView System Data MX150 User Setup System InfoStandard Transition TestingATS Testing Delayed TransitionSequence of Operation Timer Designations as they appear in the SET menuStandard and Delay Transition Controls Power Supply CPSControls Power Supply CPS cont’d Standard Transition CPS SchematicDelayed Transition CPS Schematic General Troubleshooting Troubleshooting and DiagnosticsServicing Maintenance and TestingInspection and Cleaning TestingStandard Transition 40 to 260 Amps Solenoid Type Power Panel and Replacement PartsStandard Transition 400 to 600 Amps Molded Type Power Panel and Replacement Parts cont’dARC Grid Removed for Clarity Standard Transition 800 to 1200 AmpsStationary Contact Moveable Contact Standard Transition 1600 to 3000 AmpsAmps Delayed Transition 40 to 600 AmpsSCR-EO Movable Contact Stationary Contact Delayed Transition 800 to 1200 AmpsMovable E3 Contact Stationary Delayed Transition 1600 to 3000 AmpsPage Page Page GE Zenith Controls