12Extreme Networks recommends attaching safety wire to the access point safety wire tie point or security cable (if used) to the access point’s lock port.
13Align the ceiling tile into its former ceiling space.
14Cable the access point using either the Power Injector solution or the power supply. For Power Injector installations:
a Connect a
b Connect a
c Ensure the cable length from the Ethernet source to the Power Injector and access point does not exceed 100 meters (333 ft). The Power Injector has no On/Off power switch. The Power Injector receives power as soon as AC power is applied.
For standard 48 volt power adapter (5014000247R) and line cord installations:
a Connect
b Verify the power adapter is correctly rated according the country of operation. c Connect the power supply line cord to the power adapter.
d Attach the power adapter cable into the power connector on the access point. e Plug the power adapter into an outlet.
For
a Connect an
b Ensure the cable length from the controller port to the access point does not exceed 100 meters (333 ft).
c Verify power is enabled on the controller port.
CAUTION
Do not actually connect to the power source until the cabling portion of the installation is complete.
15Verify the behavior of the access point LED light pipe. For more information, see “LED Indicators” on page 26.
16Place the ceiling tile back in its frame and verify it is secure.
Altitude 4700 Series Access Point Installation Guide | 25 |
|
|