Installation

To avoid electric shock, ground all equipment. Turn off equipment power and shut off power at main circuit breaker before installing.

All electrical wiring must be done by a qualified electrician and comply with all local codes and regulations.

Do not substitute system components as this may impair intrinsic safety.

To reduce the risk of serious injury, including fluid injection, splashing, pinching or injury from moving parts, relieve pressure before installing the kit. Fol- low the Pressure Relief Procedure in the ProMix 2KS Operation or Service manual.

Installation

Location

Install the gun flush box module enclosure (1) within 15 ft (4.5 m) of the RoboMix, to ensure that the cable (23) will reach the RoboMix. The module is approved for use in a hazardous location. See FIG. 1.

Mount the Enclosure

1.See Dimensions, page 13.

2.Ensure that the wall and mounting hardware are strong enough to support the weight of the equip- ment, fluid, hoses, and stress caused during opera- tion.

3.Using the equipment as a template, mark the mounting holes on the wall at a convenient height for the operator and so equipment is easily accessi- ble for maintenance.

4.Drill mounting holes in the wall. Install anchors as needed.

5.Bolt equipment securely.

313212A

3

Image 3
Contents 15V534 Gun Flush Box Interface Kit Contents Related ManualsOverview Installation LocationMount the Enclosure Connect Cable to Terminal Strip Install the CableAFS#2 Install the Air Flow SwitchInstall Pressure Switch two shown Install the Pressure SwitchInstall Solenoid two shown Install the SolenoidRoboMix Control Board J1 Connections Connect the Cable to the RoboMix Control BoardConnect the Gun Flush Box Replace the Cover Ground the EnclosureConnect Air Supply to Module Installation 12 Ref PartsConnect a Booth Control to the RoboMix Technical Data DimensionsGraco Information Graco Standard Warranty