MECHANICAL INSTALLATION 110TB

NEW / EXISTING CONSTRUCTION INSTALLATION PROCEDURES:

Before You Begin:

Please read and understand all of these instructions thoroughly before beginning any work.

Note that construction work for the installation of all Tannoy products must be done to local building codes by qualified, licensed installers. A local building inspector should approve any overhead installations. Tannoy assumes no liability for cause and effect of improper installation work.

Your Package Includes:

The 110TB ceiling sub is complete with rubber isolation grid around the grille perimeter to drop neatly into a properly secured, 2’ x 2’ ceiling grid without vibration or resonance.

Additional Considerations:

Survey your site and choose an installation location.

At this point, you may choose to suspend the subwoofer in free space or in a 2’ space x 2’ space dropped ceiling grid installation.

Parts/ Tools Required: (Installation Dependant)

Hanger bolts (Fig. 1). These can be purchased for installation into wood, or into metal, for example, with a Hilti™ power fastening system.

Coupling nuts, and Backing nuts (Figs. 2 & 3).

Threaded rod (Fig. 4).

Turnbuckles (Fig. 5).

Wire rope, wire rope nuts, thimbles, chain, quick-links (Figs. 5 & 6).

Wire grid ties (Fig. 8).

Note: For 2’ space x 2’ space tile bridge drop in, you will require wire grid support ties on each of the four corners of the grid immediately beside the subwoofer. This is usually accomplished by means of the same wire support tie used to support the grid and for lighting fixtures, etc. IT IS IMPORTANT TO ALWAYS TETHER THE SUBWOOFER SECURELY TO THE BUILDING’S PERMANENT STRUCTURE USING CHAIN (Fig. 9) OR WIRE ROPE. THIS IS THE SEISMIC TETHER POINT.

The list above is a suggested selection of parts only; what you require will depend on your suspension method and physical location.

The 110TB is supplied with four 3/8” closed eyebolts already attached. When suspending in free space, it is recommended that you use the same size hangers, nuts, rod, and fittings; alternately, if you are using wire rope, 1/8” rope and fittings are the smallest you should consider.

Image 12
Contents Series Subwoofers WARRANTY/DAMAGE Claims UNPACKING-DAMAGE ClaimsSeries Subwoofers and Input Modules 110TB Tile Bridge 110SR Sheet RockPage Table of Contents Cabinet Options 110TB Tile Bridge Cabinet110SR Sheet Rock Cabinet 110CS Corner Subwoofer CabinetInput Module Options Passive standardCrossover Passive 70 Volt with crossover Active active subwoofer with 2-channel feed-through Active input module is UL and CSA listedActive 110 Input Module Controls Active Module with output for 2 speakersActive 110 Input Module Controls Mechanical Installation 110TB NEW / Existing Construction Installation Procedures’ x 2’ Tile Grid Installation Procedures Installed subwoofer top view, only two chains attached Suspension points Mechanical Installation 110SR Instalation of blocking for flush mounting of PIR to joists Cutting drywall using the Rotozip SR installation Mechanical Installation 110CS Installation of Corner Rail KITSubwoofer Installation Mechanical Installation 110CS Dimensions 110TB 40 LBSDimensions 110SR 37 LBSDimensions 110CS 56 LBSTechnical Specifications Active Module Ceiling & IN-WALL Loudspeakers 0903