American Power Conversion VS 50, VS 100 user manual Pre-Commissioning Inspection, Environment

Page 21

3 Commissioning

This section is intended as a guide when powering up a system for the first time. It may not be desirable to perform some steps depending on the particular installation. Refer to the appropriate section for information relating to how these steps should be performed.

3.1.Pre-Commissioning Inspection

Environment

1.Ensure the dc system environment is suitable for operation.

2.Ensure that there is sufficient clearance around the system for service.

3.Ensure that there is no sign of damage to the dc system.

4.Disable installed alarms before servicing the unit. This will allow the unit to be serviced without creating false alarms.

Electrical Installation

1.Ensure that the dc wiring is properly installed, sized, terminated and identified.

2.Ensure that the ac wiring is properly installed, sized, terminated and identified.

3.Ensure that the battery wiring is properly installed.

4.Ensure that the dc output over-current protection devices are adequate for the size of wiring installed.

5.Ensure that the dc positive is bonded to central office ground.

6.Note the resistance of the ground bond.

7.Note any currents flowing in the ground.

8.Record ambient temperature.

9.Verify that the battery polarity is correct.

10.If a battery disconnect device(s) is/are present, note the following for each device:

a.DC voltage Rating.

b.DC Current Rating

c.Interrupting Current Rating

Battery Visual and Safety Inspection

1.Check the mechanical integrity of the battery framing, racking, or cabinet.

2.Check that the battery framing, racking or cabinet is adequately secured to the floor.

3.Check compliance with seismic zone requirements.

4.Check the general appearance and cleanliness of the battery.

5.Record the manufacturer, model number, and capacity of the battery string(s).

6.Record the batch number, date code, and serial number of each cell or mono-block, and any other pertinent information that is available on the battery cells.

7.Check that the cell or mono-block numbering starts at the positive battery string terminal and is correct.

8.Check that anti-oxidation compound is properly applied.

9.Visually inspect each cell for:

a.Cracks.

b.Case leaks.

c.Post-seal leaks.

d.Pressure relief valve leaks (VRLA only).

e.Case swelling (VRLA only).

10.Check the torque of all battery inter- cell connector in accordance with the battery manufacturer’s specifications.

Magnum VS –48 Vdc User Manual

Page 21

Image 21
Contents Magnum VS Vdc Power Systems Table of Contents Programming Output Relays Table of Figures Page General Information IntroductionDescription AccessoriesControl Power Distribution BackplaneInstallation Mechanical InstallationUnpacking Equipment AC Connections AC Power ConnectionsAC Power Cord Sets Planning the Battery installation Battery ConnectionsConnecting the Cables Recommended toCounter Electro-Motive Force Cemf Cell Connections Battery Temperature Probe Installation1 Cemf Connection Locations DC System GroundingCircuit Breaker Installation Load Protection InstallationGMT Fuse Installation Load ConnectionsGMT Fuse-protected Load Connections Circuit Breaker Protected Load Connections 30 or 60 aMonitoring and Relay Output Connections RJ45 Ethernet ConnectorFront Panel DB9 Connection Major, Minor and Relay 1 Output Connections 1 Interface Connections Output Relay 2-6 Connections2 Output Relay Connections External Alarm Input ConnectionsController Module Installation Rectifier Module InstallationBattery Visual and Safety Inspection Electrical InstallationCommissioning Pre-Commissioning InspectionDC Power Up AC Power UpCommissioning Initial Set-upRectifier Test Battery Power UpLVD Test Circuit Breaker/ Fuse TestBattery Temperature Compensation Final InspectionOutput Relay Technical Description Rectifier ManagementSystem Management Load Management System Status and Alarm ReportingSystem Current Monitor Circuit BreakersBattery Management Battery ChargingGMT Fuses Battery Temperature Monitoring Battery ProtectionBattery Low Voltage Disconnect Counter Electro-Motive Force Module ConnectionsAlarm Outputs Output Relays Controls and IndicatorsExternal Alarm Inputs User Input Network Management Card Local & Remote MonitoringOperation DescriptionController Module Jumpers 1 Controller Card Jumper Locations Controller ModuleMagnum VS Controller Operation Using the RS-232 Comm PortOperation Using the 10/100 BaseT Ethernet Port Settings in Bold Settings DefaultDistribution/Breakers 00 mVSystem/Date & Time Power Modules/RectifiersDistribution/Fuses Batteries ParametersSeconds InputOutput DisableOutput Relay System/Out-Rly/AliasSeconds, 0.00 seconds System/Preferences Programming Output Relays LVD OperationSystem Visual and Safety Inspection Preventive MaintenanceEquipment InspectionTest Battery Current Test Battery Temperature TestBattery Preventive Maintenance Procedure Final Inspection Alarm Summary System LT Alm System Temperature is below Minor Magnum VS 50 Power System SpecificationsMagnum VS 100 Power System AC InputDC Output Magnum VS Controller Environmental MechanicalCompliance APC Worldwide Customer Support Terms of Warranty Non-transferable Warranty ExclusionsWarranty Claims