APC 990-1031, SYPM2KU, SYBT2 installation manual

Page 13

Input Voltage Selection Switch : Set this switch to the appropriate setting, either 200/208 (L1-L2-G) or 220/230/240 (L1-N-G) before powering up the Symmetra RM.

Products rated 200/208 are typically installed in North America (208 V, phase to phase, grounding conductor) and Japan (200V, phase to phase, grounding conductor).

Products rated 2020/230/240 are typically installed in the rest of the world (220 V, 230 V, or 240 V, phase to neutral, protective earth). These products must be hard wired to the input power.

Maintenance Bypass Switch : When switched to the On position, the maintenance bypass switch bypasses the Symmetra RM, and causes the load equipment to be powered directly from utility power. When it is switched to the Off position, utility power flows into the Symmetra RM, and conditioned power is delivered to the load equipment. Under normal operating conditions, the maintenance bypass switch remains in the Off position.

The load equipment is unprotected when the maintenance bypass switch is in the On position.

Input Wiring Access Panels : Provides access to wiring terminal blocks for input wiring. The 200/208 (L1-L2-G) version must be hard wired if the load is greater than 5 kVA. The 220/230/240 (L1-N-G) version must always be hard wired.

Input Power Cord [on 200/208 (L1-L2-G) versions only]: The 200/208 (L1-L2-G) version can use the line cord to connect to the power source if the load is less than 5 kVA. If the load is greater than 5 kVA, the unit must be hard wired to the power source. The 220/230/240 (L1-N-G) version must always be hard wired.

9

Image 13
Contents APC Symmetra RM Installation Manual Life Support Policy Limited WarrantyTable of Contents List of Figures Electrical Safety Handling SafetyConventions Used in this Manual Battery Safety Deenergizing SafetyRadio Frequency Interference Recycling of BatteriesPage Description Option End Item SKU About Your UPSNorth America How To Contact APCLatin America, South America Europe, Middle East, and AfricaFront View Component Identification Product OverviewRear View Component Identification Use only accessory devices labeled Symmetra compatiblePage MIM System Block DiagramUnpacking Installing the Symmetra RMDetermine the Location of the Symmetra RM in the Rack Install the UPS into the Rack Connect the Symmetra RM to its Power SourceUse only a qualified electrician to install the EPO wiring Wire the Emergency Power Off EPO SwitchCL2X Install Modules Into the Symmetra RM Frame220/230/240 L1-N-G PDU Panel 200/208 L1-L2-G PDU Panel Connect Equipment to the Symmetra RMAppendix a Electrical Wiring Checklist Vin