APC SYPM2KU, 990-1031, SYBT2 installation manual Appendix a Electrical Wiring Checklist

Page 21

APPENDIX A: ELECTRICAL WIRING CHECKLIST

Complete this checklist to ensure that the Symmetra RM has been wired properly.

Ensure that all switches (system enable, maintenance bypass, input circuit breaker, and bypass circuit breaker) are in the Off or Stand By position. Turn off or unplug all equipment connected to the Symmetra RM.

Ensure that the input voltage selection switch is in the appropriate position.

1.Apply power to the system input. Measure the voltage at the input terminal block. Record the measured voltages:

L1-L2 for 200/208 Vac __________________________________________

OR

L1-Neutral for 220/230/240 Vac: __________________________________

The measured voltage must be between 184 and 265 V. If it is not, do not continue! Verify the wiring from the power source to the input wiring connections. Repeat step 1.

2. Connect the PowerView display bezel.

3. Switch the input circuit breaker, then switch the system enable switch on.

The system will make some clicking sounds as it powers up, and may display fault messages on the PowerView display. Disregard the messages at this time.

4.Press the escape key on the display until the top level menu screen appears. Select “Status.” Pressing the enter key opens the voltage status screen, shown below.

 

Vin

Vout

Iout

 

 

237.0

0.0

0.0A

 

 

 

 

 

 

The fault light on the display may remain on. Disregard this visual indicator at this time.

17

Image 21
Contents APC Symmetra RM Installation Manual Life Support Policy Limited WarrantyTable of Contents List of Figures Handling Safety Electrical SafetyConventions Used in this Manual Battery Safety Deenergizing SafetyRadio Frequency Interference Recycling of BatteriesPage Description Option End Item SKU About Your UPSNorth America How To Contact APCLatin America, South America Europe, Middle East, and AfricaFront View Component Identification Product OverviewRear View Component Identification Use only accessory devices labeled Symmetra compatiblePage MIM System Block DiagramUnpacking Installing the Symmetra RMDetermine the Location of the Symmetra RM in the Rack Install the UPS into the Rack Connect the Symmetra RM to its Power SourceUse only a qualified electrician to install the EPO wiring Wire the Emergency Power Off EPO SwitchCL2X Install Modules Into the Symmetra RM Frame220/230/240 L1-N-G PDU Panel 200/208 L1-L2-G PDU Panel Connect Equipment to the Symmetra RMAppendix a Electrical Wiring Checklist Vin