American Power Conversion 120-160kW Display shows, System OFF Normal operation load power XX%

Page 9

Stop/Start UPS and Operating the External Service Bypass

1.Check that the system has been in a stable environment for at least 12 hours enabling any condensation to evaporate prior to start-up.

2.Open front door(s)

3.Switch on mains power by closing Q001 See notice below.

4.Wait for approx. 10 seconds

5.

Press

on the keyboard

6.

Press

on the keyboard

7.Wait for approx. 1 second

8.Wait for approx. 1 minute

9.Close MCCBs in Battery Breaker Box or Battery Cabinet

10.Press the green ON button

11.Close the front door(s)

Display shows

System type XXX

XXX kVA - XXX

Stop charge DC capacitors : YES

Start charge DC capacitors : YES

Data stored

Start charge DC capacitors : YES

Insert fuse or close MCCB

**System OFF**

Normal operation load power XX%

System start-up now completed.

NOTICE!

One of the following display messages will appear by UPS start-up:

“STD”: Standard (single system)

“PAR”: Parallel System

“ECO”: Economy mode (single or parallel systems) (Last message has priority over the other two)

kVA size (XXX) and the voltage reads:

• XXXkVA - 400 (380 or 415 Volt)

 

990-4036

 

 

User Guide APC Silcon 120-160kW 400V UPS

9

Image 9
Contents Copyright 2000 APC Denmark ApS 120-160kW 400V UPS User GuideSafety Symbols used in this manual User Guide APC Silcon 120-160kW 400V UPSThank You Contents Introduction IntroductionDisplay Unit Normal operation Load power xx% Stop/Start UPS and Operating the External Service BypassStop UPS for stand-by Start UPS from stand-bySwitching off the UPS Stop UPS for complete power downBlank UPS start-up Start UPS from complete power downDisplay shows System OFF Normal operation load power XX%Operating the External Service Bypass Switch single systems Bypassing the Single System UPSBypass operation Stop/Start UPS and Operating the External Service Bypass Bypass operation Normal operation Load power 0% System OFF Normal operation Load power 0% Bypass operationBypassing the Parallel UPS System All UPSs Acoustic alarm sounds for 30 secs Stop/Start UPS and Operating the External Service Bypass Set input switches Q001 to position Press the green on button on all systemsPress On the keyboard Isolating one UPS in a Parallel/Redundant System Stop/Start UPS and Operating the External Service Bypass Operation OperationKeyboard Using the Remote Display Display of Measured ValuesBatt. load Batt. tank Economy Mode Parameter Settings Parameter SettingsParameter Settings Switching to Bypass Operation Programming KeysProgramming Example Load power xx% Alarms and Events Alarms and EventsDisplaying the Alarm Stack Mode CommentsAlarms Description Action Possible AlarmsDisplay will show invalid UPS data Rectifying Alarm Messages Parallel Operation AlarmsCorrection of false alarm situations during service Maintenance & Testing Maintenance & TestingBattery Monitoring Test Battery Capacity TestUntil Battery capacity TestTest Xxx Press Test PressWarranty WarrantyAPC Silcon UPS Limited Factory Warranty How to Contact APC How to Contact APCAPC Corporate APC Denmark