III. SHRINK-WRAP
After all other connections are completed, or correct wire lengths verified, complete the
a.Position the
b.Heat treat the
NOTE
On pole mounts, secure the cable exiting the cabinet to the pole using standard practices and
Proceed with Step 5 of the Splice Wires sub section.
5.Insert the circuit pack into the desired slot. The card’s edge connector is offset and must be properly aligned to ensure connectivity.
CAUTION
The FPU at the CO must be online for fan operation. For the best cooling results, fully load the top shelf with circuit cards before loading the bottom shelf.
6.Connect the wiring in cable stubs based on the appropriate matching slot used.
7.Refer to Table 5A and 5B for splice module connections and Table 6A and 6B for Circuit Technology Configuration charts. Table 5 also provides circuit and pair identification to configure the cards listed in the table.
NOTE
Refer to the 3M MS2 ™ Modular Splicing System Instructions Booklet for splicing and connecting to
8.Connect the ground lug on the bottom of the cabinet to an appropriate 6 AWG ground cable and earth ground.
CAUTION
Without positive ground the cabinet does not provide surge protection.
9.Inspect and clean the door gasket and gasket sealing area prior to closing the front or rear doors. If there is visible damage, replace the door gasket.
10.Tighten the tamper resistant security screws on the front and rear doors using a 7/16 inch nut driver or an equivalent tool. While loosening or tightening the security screws, alternate between the top and bottom screws to allow even pressure. Tighten to