Installation Instructions | Model |
INSTALLATION (100mm x 100mm)
Flush Mount Centris Bracket to Display
1.Install two M4 x 12mm screws (60) into the top mounting holes (not shown) on the display .
2.Align the mounting holes on the Centris bracket with the screws installed on the display. Hang the display on the Centris bracket. (see figure 4)
3.Install two remaining M4 x 12mm screws (60) into the bottom mounting holes on the display.
Recess Mount Centris Bracket to Display
Use one of the following screw and spacer combinations: (40 with 100) or (50 with 110).
CAUTION: If your display uses a screw size other thanM4 x 20mm or M4 x 30mm, DO NOT use the M4 x 20mm or M4 x 30mm screws. Using the wrong screws
60
Display
Centris Bracket
could result in damage to your display.
1.Select four M4 screws (40 or 50) and four retaining spacers (100 or 110) from parts bag.
2.Place display face down on a clean dry surface.
3.Install four M4 screws (40 or 50) into the four mounting holes on centris bracket.(see figure 6)
4.Slide 4 retaining spacers (100 or 110) onto four M4 screws (40 or 50).
5.Align centris bracket, with screws (40 or 50) and spacers (100 or 110), with mounting holes in display back.
6.Tighten all screws.
Figure 4: Flush Mount Centris Bracket to Display
40 or 50
100 or 110
Figure 5: Recess Mount Centris Bracket to Display
7