Spalding M8872411 manual Make sure nuts 25 are 2.75 7 cm from top of J-bolts

Page 5

1.

Ensure ground is level with playing surface, then dig pole hole.

24" (61 cm)

WARNING!

GROUND SURFACE

24" (61 cm)

48" (121.9 cm)

PLAYING SURFACE

CONTACT UTILITIES BEFORE DIGGING.

48" (121.9 cm)

2.

Install nut (25) to J-bolt (19) as shown. Repeat procedure for remaining three J-bolts (19).

IMPORTANT!

Make sure nuts (25) are 2.75” (7 cm) from top of J-bolts

25

19

2.75”

(7 cm)

25

2

25

3.

Install threaded ends of J-bolts (19) through holes

 

 

in mounting plate (2) and secure as shown.

 

 

 

19

 

 

 

 

 

 

NOTE:

Make sure J-bolts (19) are in the illustrated position.

Nuts on the top of plate are used for leveling the pole after system is fully assembled.

5

09/05

ID# M8872411

Image 5
Contents High End Residential In-Ground Basketball System Safety Instructions Parts List Hardware Identifier Bolts & Screws Make sure nuts 25 are 2.75 7 cm from top of J-bolts Build drainage hill Side V IEWShown Insert bushings 38 into areasMounting plate 2 as shown Playing SurfaceCompleted Assembly ID# M8872411 09/05 Lower yoke Attach elevator adjustment 12 toAttach elevator adjustment 12 to pole bracket Attach backboard 10 to upper and lower Using TWO people to hold the boardYokes 18 First attach board 10 to upper yokeEnd of the rod 14 as shown Figure a Attach height indicators Apply height indicator labels 32 & 31 to height indicatorsInstall net 4 to rim as shown To lower yoke in areaNing 09/05 ID# M8872411 Should be level in all directions Check system leveling. PoleLimited Lifetime Warranty