2.Multiple Dryer (Common) Venting

If it is not feasible to provide separate exhaust ducts for each dryer, ducts from individual dryers may be channeled into a common main duct. The individual ducts should enter the bottom or side of the main duct at an angle not more than 45º in the direction of the airflow.

IMPORTANT: No more than eight (8) dryers should be connected to one (1) main common duct.

NOTE: Refer to the illustration on page 15 for examples of multiple dryer (common) venting.

The main duct may be any shape so long as the minimum cross-sectional area is provided. The illustration on page 15 shows the minimum cross-sectional area for multiple dryer venting. These figures must be increased in proportion if the main duct run from the last dryer to where it exhausts to the outdoors is unusually long (over 20 feet [6.1 meters]) or has numerous elbows (more than one [1]) in it.

IMPORTANT: For extended duct work runs, the cross-sectional area of the duct work can only be increased to an extent. Maximum proportional duct work runs cannot exceed 20 feet (6.1 meters) more than the original limitations of 20 feet (6.1 meters) with one (1) elbow. When the duct work approaches the maximum limits as noted in this manual, a professional heating, venting, and air-conditioning (HVAC) firm must be consulted for proper venting information.

IMPORTANT: Exhaust back pressure measured by a manometer at the dryer’s exhaust duct area must not exceed 0.3 inches of water column (W.C.) - 0.74 mb - when both baskets (tumblers) are operating.

The duct work should be smooth inside with no projections from sheet metal screws or other obstructions which will collect lint. When adding ducts, the duct to be added should overlap the duct to which it is to be connected. ALL duct work joints must be taped to prevent moisture and lint from escaping into the building. Also, inspection doors should be installed at strategic points in the exhaust duct work for periodic inspection and cleaning.

NOTE: When the exhaust duct work passes through a wall, ceiling, or roof made of combustible materials, the opening must be 2-inches (5.08 cm) larger than the duct (ALL the way around). The duct must be centered within this opening.

To protect the outside end of the horizontal duct work from the weather, a 90º elbow bent downward should be installed where the exhaust exits the building. If the exhaust duct work travels vertically up through the roof, it should be protected from the weather by using a 180º turn to point the opening downward. In either case, allow at least twice the diameter of the duct between the duct opening and nearest obstruction.

14

Image 18
Contents MLG32PD3 Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Section Procedure for Functional Check Section Important InformationSafety Precautions What to do if YOU Smell GASPage Specifications GAS Installation Procedures UNPACKING/SETTING UPLocation of the Dryer Page Dryer Enclosure Requirements Fresh AIR SupplyPage Exhaust Requirements 882099 Page 882099 Electrical Information Electrical RequirementsBlack White Green Electric Service Specifications PER Tumbler GAS Information 23,940 kcal/hr Page Preparation for Operation Preoperational TestsInches Water Column 26.1 mb Shut Down Instructions Basket CoatingOperating Instructions Starting the DryerSERVICE/PARTS Information ServiceParts Warranty Information Returning Warranty CardsWarranty Routine Maintenance CleaningVoid the Warranty Adjustments LubricationDryer Data Label Information Data Label LocationData Label Serial Number Procedure for Functional Check Replacement Components Part No 1- 11/03/00-50