2.Multiple Dryer (Common) Venting

If it is not feasible to provide separate exhaust ducts for each dryer, ducts from individual dryers may be channeled into a common main duct. The individual ducts should enter the bottom or side of the main duct at an angle not more than 45° in the direction of the airflow.

IMPORTANT: No more than eight (8) dryers should be connected to one (1) main common duct.

NOTE: Refer to the illustration on the next page for examples of multiple dryer (common) venting.

The main duct may be any shape so long as the minimum cross-sectional area is provided. The illustration on the next page shows the minimum cross-sectional area for multiple dryer venting. These figures must be increased in proportion if the main duct run from the last dryer to where it exhausts to the outdoors is unusually long (over 20 feet) or has numerous elbows (more than one [1]) in it.

IMPORTANT: For extended ductwork runs, the cross-sectional area of the ductwork can only be increased to an extent. Maximum proportional ductwork runs cannot exceed 20 feet more than the original limitations of 20 feet with one (1) elbow. When the ductwork approaches the maximum limits as noted in this manual, a professional heating, ventilation, and air-conditioning (HVAC) firm should be consulted for proper venting information.

IMPORTANT: Exhaust back pressure measured by a manometer at the dryer’s exhaust duct area must be no less than 0 and must not exceed 0.3 inches of water column (W.C.) when both baskets (tumblers) are operating.

The ductwork should be smooth inside with no projections from sheet metal screws or other obstructions, which will collect lint. When adding ducts, the duct to be added should overlap the duct to which it is to be connected. ALL ductwork joints must be taped to prevent moisture and lint from escaping into the building. Also, inspection doors should be installed at strategic points in the exhaust ductwork for periodic inspection and cleaning.

NOTE: When the exhaust ductwork passes through a wall, ceiling, or roof made of combustible materials, the opening must be 2-inches larger than the duct (all the way around). The duct must be centered within this opening.

To protect the outside end of the horizontal ductwork from the weather, a 90° elbow bent downward should be installed where the exhaust exits the building. If the exhaust ductwork travels vertically up through the roof, it should be protected from the weather by using a 180° turn to point the opening downward. In either case, allow at least twice the diameter of the duct between the duct opening and nearest obstruction.

14

Maytag Co.

113062 - 16

Image 18
Contents MLG32PDB Installation Manual Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Warranty Information Important Information Receiving and HandlingSafety Precautions What to do if YOU Smell GASMaytag Co Specifications SpecificationsSpecifications Installation Procedures UNPACKING/SETTING UPLocation of the Dryer Maytag Co Dryer Enclosure Requirements Fresh AIR Supply RequirementsMaytag Co Exhaust Requirements Gauge 0.0195-inches 0.50 mm thick Maytag Co 113062 Maytag Co Electrical Information Electrical RequirementsSingle-Phase 1Ø Electrical Connection Leads Electrical Service Specifications PER Tumbler GAS Information Type of GAS Maytag Co Preparation for Operation Preoperational TestsNatural Gas Inches Water Column Liquid Propane L.P. Gas Shutdown Instructions Basket Tumbler CoatingOperating Instructions Starting the DryerSERVICE/PARTS Information ServiceParts Warranty Information Returning Warranty CardsWarranty Routine Maintenance CleaningSuggested Cleaning Schedule Adjustments LubricationDryer Data Label Information Data Label LocationData Label 16 08/08/08