2.MULTIPLE DRYER (Common) VENTING
If it is not feasible to provide separate exhaust ducts for each dryer, ducts from individual dryers may be channeled into a "common main duct." The individual ducts should enter the bottom or side of the main duct at an angle not more than 45º in the direction of the airflow. The main duct should be tapered, with the diameter increasing before each individual
IMPORTANT: No more than eight (8) dryers should be connected to one main common duct.
NOTE: Refer to the illustration on page 15 for examples of multiple dryer (common) venting.
The main duct may be any shape so long as the minimum
IMPORTANT: For extended duct work runs, the cross section area of the duct work can only be increased to an extent. Maximum proportional duct work runs cannot exceed 20 feet more than the original limitations of 20 feet with two (2) elbows. When the duct work approaches the maximum limits as noted in this manual, a professional HVAC firm should be consulted for proper venting information.
IMPORTANT: Exhaust back pressure measured by a manometer at each basket (tumbler) exhaust duct area should not exceed 0.3 inches W.C. (water column).
The duct work should be smooth inside with no projections from sheet metal screws or other obstructions which will collect lint. When adding ducts, the duct to be added should overlap the duct to which it is to be connected. ALL duct work joints must be taped to prevent moisture and lint from escaping into the building. Also, inspection doorsshould be installed at strategic points in the exhaust duct work for periodic inspection and cleaning.
NOTE: Where the exhaust passes through a wall, ceiling, or roof made of combustible materials, the opening must be
To protect the outside end of the horizontal duct work from the weather, a 90º elbow bent downward should be installed where the exhaust exits the building. If the exhaust duct work travels vertically up through the roof, it should be protected from the weather by using a 180º turn to point the opening downward. In either case, allow at least twice the diameter of the duct between the duct opening and nearest obstruction.
14