CHAPTER 4: INSTALLATION
Unpacking
The UPS and accompanying components is packaged in a robust shipping carton. Carefully remove the package contents. The UPS and modular components are shipped on one or more pallets, depending on the configuration. The packaging is recyclable; save it for reuse or dispose of it properly.
Inspection
Inspect the equipment upon receipt. APC has designed robust packaging for your product. However, accidents and damage may occur during shipment. Notify the carrier and dealer if there is damage or missing equipment.
Contents
Check the packaging contents. Two shipping pallets are included:
(1)Boxed UPS,
•Transportation cart
•Rail kit (containing the mounting rails and hardware),
•Accessory bezel kit (containing two transportation cart brackets, display bezel with Powerview, four blank bezels, blank panel kit, and literature kit
(2)Individually boxed and
Installing the UPS
This section provides information on the steps required to install and connect the UPS.
The UPS is designed for use in a data center or other office environment. Refer to Chapter 3: Site Preparation to select a location.
Moving the UPS to the Installation Site
•The UPS is heavy. Two people, one on each side, must support the UPS when it is being transported on the cart to the rack; installed, or removed from the rack.
•A qualified electrician must install or remove battery modules.
•Two people are required to lift, move, install, or remove battery and power modules. The battery and power modules are heavy.
Do not install battery modules until you are ready to power up the UPS. Batteries can be permanently damaged if loaded prematurely.
•To comply with FAA regulations, the battery modules are shipped disconnected to the UPS.
•Mounting rails are included with the UPS. The rails support the unit in the rack.