Emerson SZV44 Initial Startup Compressor Module, Pre-Startup Checklist, Post-Startup Checklist

Page 21

Dual-Compressor Module

Operation

3.0Operation

3.1Initial Startup - Compressor Module

The following inspections should be made on initial startup—-typically, by the Packager—and after long periods of storage.

Verify acceptable pre-startup conditions using the checklist in 3.1.1 - Pre-Startup Checklist.

Start the Compressor Module, then perform the checks in 3.1.2 - Post-Startup Checklist.

3.1.1Pre-Startup Checklist

Perform these checks BEFORE starting the Compressor Module:

MAIN POWER

Check for the following conditions:

___ 1. Motor type is correct for the application, either Variable Speed (275V) or Fixed Speed motor (480V).

___ 2. Power phasing to the terminal strip and Compressors is correct.

___ 3. Supply voltage to the Variable Frequency Drive (VFD) or Fixed Speed Compressor motors is correct.

___ 4. Each Compressor motor is equipped with current overload protection.

___ 5. Compressor motor overloads are configured to inhibit the VFD or either fixed speed Compressor if either motor overload opens.

___ 6. Compressor motor overloads are configured for manual reset.

___ 7. Compressor motor overloads are set for proper current.

___ 8. All chassis, earth grounds are connected.

___ 9. A load reactor or other approved filter is installed for systems with power lead lengths in excess of 200 ft. (61m) between the VFD and Compressor Module terminal box.

LOW VOLTAGE DEVICES

Verify these conditions for low voltage devices:

___ 1. DC polarity is correct.

___ 2. Temperature control device—if other than standard thermistor control—is working properly.

SAFETY AND CONTROL DEVICES

Make sure that all safety and control switches and devices are configured to inhibit Compressor operation if a fault condition is detected, including:

___ 1. Low inlet pressure switch

___ 2. High discharge pressure switch

___ 3. High temperature switch

___ 4. Variable Frequency Drive (VFD) fault

___ 5. Motor overload trip

___ 6. Other safety and control switches and devices

MECHANICAL SYSTEMS

Inspect for these conditions:

___ 1. (Required) Compressor inlet is protected from water slugging.

___ 2. (Recommended) Gas filtration and treatment is appropriate for the application.

___ 3. Packager configuration applies back pressure to the Compressors.

___ 4. Inlet and discharge valves allow the module to be isolated.

___ 5. All guards and protective covers are installed.

___ 6. Protection from freezing is provided if needed for the application and location.

___ 7. A suitable enclosure providing protection from the elements is appropriate for the application and location.

3.1.2Post-Startup Checklist

Perform these checks AFTER starting the Compressor Module:

DURING INITIAL OPERATION, PERFORM THESE CHECKS:

___ 1. Compressor Module builds pressure on initial startup; no unusual mechanical noise.

___ 2. Oil level is correct at minimum and maximum speeds.

___ 3. No gas leaks are present.

___ 4. No oil leaks are present.

___ 5. Oil cooler fans turn on and run at the appropriate temperature.

___ 6. Oil cooler fan speed varies with temperature.

___ 7. Compressor motor speed varies appropriately for the Packager configuration.

___ 8. Compressor continues to operate in bypass when the Compressor Module discharge is blocked.

___ 9. Compressor Module is leak tight (maintains approximately 30 psig or more when the Compressors are initially turned off).

15

2006SSD-75 R4 (10/10)

Image 21
Contents Copeland Scroll Compressor Module Page Table of Contents Appendix A Material Data Safety Sheet Figures Compressor Module Nomenclature Important Safety Information Safety Symbols Used in This Manual Safety Alert SymbolCompressor Module IntroductionOil coolers with fans Compressor Compressor PackageInlet gas scrubber for liquid removal General Installation Guidelines Installation GuidelinesInlet and Discharge Pressures Required Component-Inlet Gas ScrubberAmbient Temperature Range Barg SettingModule Weight Lbs. kg Compressor Module Dimensions, in. mm Installation Clearance and DimensionsCode Description Process and Instrumentation Diagrams P&IDsSwitchStatus SwitchesElectrical Controls General ConsiderationsBrushless DC Fan Oil Cooler Fan ControlSZO44 Temperature ControlDrive Variable SpeedTypical Compressor Module power supply requirements Compressor Power data based on 480VAC Variable SpeedElectrical Requirements Control Circuit Terminations WiringPost-Startup Checklist Pre-Startup ChecklistInitial Startup Compressor Module OperationCheck for These Conditions Under Normal Operation Routine Maintenance MaintenanceMaintenance summary Maintenance Tools Maintenance ToolsOil Capacity and Type Checking the Oil LevelOil Level Guidelines Minimum Speed Oil Level Guidelines Maximum SpeedAdding and Removing Oil Topping Off the Oil LevelAdding Oil Draining Oil Changing the OilReplacing Oil Servicing the Scavenge Line Orifice Cleaning the Inlet ScreenChanging the Oil Filter Element Changing the Second-Stage Separator ElementTroubleshooting Troubleshooting GuideMotor Winding Resistance Motor winding resistancePlatform troubleshooting guidelines Platform Symptoms DiagnosisSpecifications Compressor Module Specifications Dual-Compressor Module Technical Support and Service Max Flow/HP as a function of discharge Configuration Suction130 140 110110 120 Flow rate150 180Supplier Appendix A - Material Data Safety SheetEmergency Number 989 Product Name and Information Components and Hazard StatementFire and Explosion Hazards Spill or Leak ProceduresReactivity Data Health Hazard DataPage Page EmersonClimate.com