4.1SENSOR PREPARATION

4.2pH CALIBRATION

4.3ORP CALIBRATION

4.1SENSOR PREPARATION

Shake down the sensor to remove any air bubbles that may be present in the tip of the pH glass bulb. In most cases, the pH sensor can simply be installed as shipped, and readings with an accuracy of ± 0.6 pH may be obtained. To obtain greater accuracy or to verify proper operation, the sensor must be calibrated together with its compatible analyzer or transmitter.

4.2pH CALIBRATION

After a temporary connection is established between the sensor and the instrument, a buffer calibration may be performed. Consult the appropriate pH/ORP analyzer or transmitter instruction manual for specific calibration and standardization procedures, or see below for recommended two-point buffer calibration procedure.

Recommended two-point buffer calibration procedure:

Select two stable buffer solutions, preferably pH 4.0 and 10.0 (pH buffers other than pH 4.0 and pH 10.0 can be used as long as the pH values are at least two pH units apart).

NOTE

A pH 7.0 buffer solution reads a mV value of approximately zero, and pH buffers read approximately

59.1 mV for each pH unit above or below pH 7.0. Check the pH buffer manufacturer specifications for mil- livolt values at various temperatures, since it may affect the actual value of the buffer solution mV/pH value.

1.Immerse the sensor in the first buffer solution. Allow the sensor to adjust to the buffer temperature (to avoid errors due to temperature differences between the buffer solution and sensor temperature) and wait for the reading to stabilize. The value of the buffer can now be acknowledged by the analyzer/transmitter.

2.Once the first buffer has been acknowledged by the analyzer/transmitter, rinse the buffer solution off of the sensor with distilled or deionized water and/or a small quantitiy of the next buffer solution.

3.Repeat steps 1 and 2 using the second buffer solution.

4.Once the analyzer/transmitter has acknowledged both buffer solutions, a sensor slope (mV/pH) is established (the slope value can be found within the analyzer/transmitter).

5.The slope value should read about 59.1 mV/pH for a new sensor and will decrease over time to approximate- ly 47-49 mV/pH. Once the slope reads below the 47-49 mV/pH range, either clean the sensor and recalibrate for a better slope or install a new sensor to maintain accurate readings.

Recommended pH Sensor Standardization:

For maximum accuracy, the sensor can be standardized online or with a process grab sample after a buffer cali- bration has been performed and the sensor has been conditioned to the process. Standardization accounts for the sensor junction potential and other interferences. Standardization will not change the sensor's slope but will simply adjust the analyzer's reading to match that of the known process pH.

1.While obtaining a process solution sample (it is recommended that the sample be taken close to the sensor), record the pH value that is shown on the analyzer/transmitter display.

2.Measure and record the pH of the process solution sample with another temperature compensated, calibrat- ed pH instrument. For best results, standardization should be performed at the process temperature.

3.Adjust the analyzer/transmitter value to the standardized value.

19

Image 23
Contents Combination pH/ORP Sensor Essential Instructions Hazardous Area InstallationModel 399VP pH/ORP Sensor Table of ContentsList of Tables List of FiguresGraph A. Pressure/Temperature Limitations For Model 399VP Section Description and SpecificationsFeatures and Applications Physical SpecificationsOrdering Information Mounting Accessories optionalMounting Guidelines Section InstallationUnpacking and Inspection MountingSensor Dimensions Model 399VP Shown in Various Flow Through Installations FLOW-THROUGH InstallationsModel 399VP Shown in LOW Flow Cell Assembly PN Insertion InstallationsAdapter PN Submersion InstallationsSensor Shown in Handrail Mounting Assembly PN JET Spray Cleaner PN Used with Model 399VP SCL Section WiringWire and Connector Pin Functions Model 54 Wiring Model 81 Wiring through Remote Junction Box 13. Model 1054 Wiring 17. Model SCL-P/Q Wiring 41055107 41055108 23. Preparation of Extension Cable PN Recommended pH Sensor Standardization Recommended two-point buffer calibration procedureSection START-UP and Calibration Sensor Preparation268 264 260 General Section MaintenanceAutomatic Temperature Compensator ORP Platinum Electrode Check PH Electrode CleaningProblem Probable Cause Remedy Section TroubleshootingGeneral Section Return of MaterialSensor or Circuit Board only Return of Materials RequestAdditional Sales Offices Americas HeadquartersASIA-PACIFIC EUROPE, Middle EAST, and AfricaWarranty Specifications subject to change without notice