COIL
SENSING
BULB
EQUALIZER
TUBE
| THERMOSTATIC |
|
| EXPANSION |
|
| VALVE |
|
| A91277 |
|
→ | Fig. |
|
| 8. Install vapor elbow (see Fig. 5B) with equalizer adapter to |
|
| suction tube of line set and suction connection to indoor coil. |
|
| Adapter has a | → |
| tube. | |
|
|
9.Connect equalizer tube of TXV to
10.Attach TXV bulb to horizontal section of suction line using bulb straps provided. (See Fig. 5C.) Insulate bulb with
11.Proceed with remainder of unit installation.
→FAN COIL
To obtain efficiency rating for 38TDB037 with FV4ANB006 fancoil TXV must be replaced with factory supplied TXV.
Replacing
→1. Remove any existing refrigerant and ensure coil has not been exposed to atmospheric pressure for more than 15 minutes.
2.Remove coil access panel and fitting panel from front of cabinet.
3.Remove and save TXV support clamp using the
B
INLET
D A
COIL
E
BULB
INSULATION
TAPE
C
A01418
Fig. 5—TXV Kit Contents
SENSING BULB
STRAP
8 O'CLOCK | 4 O'CLOCK |
A00399
Fig. 6—Positioning of Sensing Bulb
4.Remove TXV using a backup wrench on flare connections to prevent damage to tubing.
5.Using wire cutters, cut equalizer tube off flush with vapor tube inside cabinet.
6.Remove bulb from vapor tube inside cabinet.
7.Braze equalizer
IMPORTANT: Route the equalizer tube of the approved Puron® TXV through suction line connection opening in fitting door prior to replacing fitting panel around tubing.
8.Install TXV (Fig. 5A) with
9.Reinstall TXV support clamp (removed in item 3).
10.Attach TXV bulb to vapor tube inside cabinet, in same location as original was when removed, using supplied bulb straps. (See Fig. 5C.) See Fig. 6 for correct positioning of sensing bulb. Insulate bulb with
11.Route equalizer tube through suction connection opening (large hole) in fitting panel and install fitting panel in place.
12.Sweat inlet of TXV, marked “IN” to liquid line. Avoid excessive heat which could damage valve.
13.Install vapor elbow (see Fig. 5B) with equalizer adapter to vapor line of line set and vapor connection to indoor coil. Adapter has a
14.Connect equalizer tube of TXV by
15.Proceed with the remainder of unit installation.
LONG-LINE APPLICATIONS
For refrigerant piping arrangements with equivalent lengths greater than 50 ft or when elevation difference between indoor and/or outdoor unit is more than 20 ft, follow all requirements of the
Step 6—Make Piping Connections
Relieve pressure and recover all refrigerant before system repair or final unit disposal to avoid personal injury or death. Use all service ports and open all
3