Lochinvar Hot Water Generator 6Maintenance, Strainers - inspection and replacement

Page 20
Strainers - inspection and replacement

Hot Water Generator Installation and Operation Manual

6Maintenance

Temperature control valve (optional) - inspection and replacement

The temperature control valve is installed adjacent to the tube bundle. The manufacturer’s documentation included with the unit gives specifics for operation and maintenance of the control valve. The CAD drawing included with the unit will give the exact location, as well as interlocks with other components. This information should be reviewed before removal / replacement of the temperature control valve.

7.

Remove the temperature control valve from the system.

8.

Follow the supplied manufacturer instructions for

 

inspecting the valve. If found to be malfunctioning,

 

replace the valve.

9.

Carefully replace the temperature control valve into the

 

system by reattaching it to the energy source inlet line and

 

the tube bundle outlet line. Follow recommendations

 

contained in the manufacturer’s documentation, local

 

codes, or accepted contractor practices as to the use and /

 

or type of joint compound or sealer at the connections.

￿WARNING

Steam or boiler water present situations that can be very dangerous because of the high temperatures and pressures. Use common sense and follow all accepted and

recommended procedures when performing installation, operation, and maintenance procedures to avoid possible injury or death.

10.

Align the valve as it was situated before removal and

 

tighten the connections. If lines were broken at an

 

additional location to allow for removal of the valve, be

 

sure to also tighten those connections.

11.

Reconnect the temperature control valve to the system

 

interlocks and install the sensing probe into the tank.

￿WARNING

The combination of electricity and water can pose a very dangerous situation. Turn off / disconnect all electric power before attempting any maintenance procedure.

￿WARNING

If the unit is equipped with a circulating pump, the pump relay must be interlocked with the temperature control valve so that the energy source will shut off if the pump is not operational. Failure to do so could

1.Follow Steps 1 through 5 of the shutdown procedure (page 10) to take the unit off-line before attempting to remove and inspect the temperature control valve.

2.Assure that the energy source, condensate / water return line, cold water inlet, and hot water outlet have been shut off; that the tank has been completely drained; that the pressure has been bled from both the water and energy source systems; and that all components and surfaces have cooled.

3.If the temperature control valve is electrically activated, turn off the power and disconnect the leads to the valve.

4.Remove the control valve probe from the tank port.

5.Carefully break the joints between the temperature control valve and the unions on either side of the valve per FIG.’s 5 and 6 on page 6 of this manual.

6.Carefully break the connections between the energy source inlet line and the tube bundle.

NOTICE

It may be necessary to break the lines at

a second location, and for the lines to be

 

 

rotated to allow clearance for the

 

temperature control valve to be

 

removed from the system. If it is

 

necessary, care should be taken to

 

ensure that in-line components are not

 

damaged.

create a very dangerous situation if the pump were to fail.

12.Follow the startup procedure (page 10) to put the unit back on-line. Carefully check all connections for any sign of leakage.

Strainers - inspection and replacement

The strainers are installed upstream of the energy source shutoff valve for the main traps. These strainers must be blown down periodically (approximately every three (3) to six

(6) months) to prevent the build up of any sediment.

The combination of electricity and water ￿ WARNING can pose a very dangerous situation. Turn

off / disconnect all electric power before attempting any maintenance procedure.

1. Follow Steps 1 through 5 of the shutdown procedure (page 10) to take the unit off-line before attempting to replace the energy source strainers.

2. The location of the strainers can differ between packages. Reference FIG.’s 3 and 4 on page 5 of this manual to identify the location of the strainers on the unit.

3. Carefully break the line connections on the inlet side of both strainers.

4. Carefully break the line connection on the outlet side of the strainers.

5. Remove and examine the strainers.

Manual background 20 Manual background

Image 20
Contents HOT WATER GENERATOR Unit shown with optional control packageDANGER ContentsHazard definitions Hot Water Generator Installation Instructions 1General informationAvailability Optional control packages see page 1General informationFigure 1 Vertical Tanks Figure 2 Horizontal Tanks Options1General information continued Figure 3 Steam to Water Optional Control PackageFigure 4 Water to Water Optional Control Package WARNING Areas of potential danger2Installation Transporting and unpacking the unitFigure 5 Steam to Water Storage Heater Figure 6 Water to Water Storage Heater2Installation continued Examining the unitMounting the unit Unit and componentsConnecting the energy source Piping the relief valves to drain2Installation Steam or boiler waterCompleting installation 2Installation continued3Operation Startup procedureShutdown procedure 4Inspection RECOMMENDED INSPECTIONSTime Interval Power Connections5Troubleshooting SYMPTOMPROBABLE CAUSE CORRECTIVE ACTION5Troubleshooting continued SYMPTOMPROBABLE CAUSE CORRECTIVE ACTION5Troubleshooting SYMPTOMPROBABLE CAUSE CORRECTIVE ACTION6Maintenance Storage tank maintenance6Maintenance Magnesium anode rod inspectionFigure 7 Horizontal Storage Tank w/Anodes Figure 8 Vertical Storage Tank w/AnodesFigure 9 Pump Wiring Diagram 6Maintenance continuedComponents replacement 6Maintenance Power connections - rewiringTube bundle - inspection and replacement replacement6Maintenance continued 5.Replace the damaged section of line or valve6Maintenance Strainers - inspection and replacement6Maintenance continued Traps - replacement steam systems only7Notes 7Notes HWG-i&o-01 CP-2M-12/05