Raypak 241275 manual Injection Pump Cover Installation, Before Starting

Page 12

Injection Pump Cover

Installation

Before Starting

1)Turn off power to the unit at the circuit breaker.

2)Turn off gas supply.

3)Shut off the water supply to the heater and, if nec- essary, drain water from the system.

4)Allow heater to cool down before attempting work.

In order to install the pump cover, you will need to rotate the pump body so that the electrical box is point- ing downward, as outlined in the following steps:

1.Loosen and remove the eight (8) 9/16” wrench bolts holding the pump body in place. See Fig. 12.

Fig. 12: Remove the eight bolts holding the pump body

in place

2.Remove the pump body then rotate it so that the electrical box is pointing downward, ensuring not to damage the seal. See Fig. 13, 14 and 15.

Fig. 13: Remove the pump body

Fig. 14: Be sure not to damage the seal when removing

or replacing the pump body

12

Image 12
Contents Installation and Operating Instructions Page General Safety Time/Temperature Relationships in ScaldsInstallation Cold Water StartConnecting Power to the Controller OperationMode Selection Switch Cold Start Sequence OperationTroubleshooting Elodrive Actuator Rotation Knob SettingCold Water Start Troubleshooting Guide Wiring Diagram Cold Water RUN Injection & Heater Pump Comparison Hi Delta Model PumpInjection Pump Cover Installation Before StartingPlace the cover on the pump Typical Boiler Piping Hi Delta shown START-UP Procedure Sequence of OperationWiring Diagram Cold Water Run Troubleshooting Guide StepIllustrated Parts Lists Cold Water StartCall OUT Description HI Delta MVB Cold Water Run Call Description HI Delta MVB OUT